CI# 28726 - P-128.10 - NSPI WO - HYD Carlton Lake Refurbishment - $3,978,895
What's happened
Filing Timeline
-
DecisionNSUARB approved Nova Scotia Power's $3,978,895 capital expenditure for Carlton Lake Dam refurbishment to meet Canadian Dam Association safety guidelines and DFO fish passage requirements.
The filings themselves
Documents
Key documents
1 file
- 05130 Board Decision Letter 9/8/2010
Exhibits
2 files
- N-1 Redacted Application 6/28/2010
- N-1(C) Confidential Application 6/28/2010
Other documents
1 file
- 05130 Board Decision Letter 9/8/2010
What's discussed — click to drill in
Topics
Infrastructure Planning
18 passages across 1 documents
Capital Expenditures
13 passages across 3 documents
Asset Management
5 passages across 1 documents
Contract Terms
3 passages across 1 documents
Power Infrastructure
3 passages across 1 documents
Confidentiality
2 passages across 1 documents
Cost Considerations
2 passages across 1 documents
Cost To Customer
2 passages across 1 documents
System Reliability
2 passages across 1 documents
Harmonized Sales Tax
1 passages across 1 documents
Procurement Practices
1 passages across 1 documents
Regulatory Approval Processes
1 passages across 1 documents