Request IR-7:
Request IR-7: - Has NS Power conducted an analysis to assess whether the differing rebate structures result in materially different outcomes for ratepayers in similarly situated areas? If so, please provide the - results of this analysis.

AI summary Request IR-7 asks NS Power whether it has analyzed if differing rebate structures lead to materially different outcomes for ratepayers in similar areas and requests the results of such an analysis.

100223Submissions - CA 1 passage
Section 5 p. p. 2
. Maintain improvements in turnaround times. NS Power notes average inspection times improved from 4-6 weeks to 2 weeks in 2024 and the 2 week average target will be maintained in 2025.[11](#page-2-0) Based on NS Power's evidence and respo...

AI summary NS Power has improved inspection times from 4-6 weeks to 2 weeks in 2024, and aims to maintain this target in 2025. However, the implementation of the Letter of Intent may not fully resolve concerns about service timeliness due to impacts from a recent cybersecurity incident. NS Power and Bell have not yet executed a final agreement, with formalization expected in 2026.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →