D-7Meter Discrepancy Analysis 1 passage
Section 3
The lifetime difference between the two meters is 53,806 kWh. At $0.17/kWh, this equals an estimated cost difference of approximately $9,147. Because both units were built and occupied at the same time, the difference is significant and sh...

AI summary The text highlights a significant difference in energy consumption between two meters, with a lifetime difference of 53,806 kWh and an estimated cost difference of approximately $9,147. This discrepancy is notable and should be investigated, particularly in conjunction with the breaker-off test, which is described as the strongest technical indicator of the issue.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →