Matter: Nova Scotia Power Inc. - CI C0051136 – TUC2 HP/IP Turbine Refurbishment – $5,965,028 (ATO)
1 passage 1 document

Distribution Planning across all matters →

976952025 Q1 Capital Report 1 passage
1st Quarter Overview - as of March 31, 2025
1st Quarter Overview - as of March 31, 2025 ACE Plan Reference Submission or Approved Transmission C0041807 L5534 Replacements and Upgrades P&A OTQ - December 5, 2022 $ - $ 1,426,418 $ 1,555,748 Approved Approved Transmission Transmission...

AI summary The 1st Quarter Overview as of March 31, 2025, outlines several approved capital expenditure projects across transmission, distribution, and generation, including replacements, upgrades, and refurbishments. Each entry includes project details, approval status, associated costs, and references to orders and quarters.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →