N-2NSPI (NSEB) RIR 1 to 3 - Redacted
8 passages
2.4.1 Observations The outer and inner lengths of each stoplog opening (in the left-right direction) were measured during the site visit using a steel measuring tape. As previously noted, the stoplog checks for Bays 1, 3, 4, and 5 could no...
AI summary During a site visit, measurements of stoplog opening lengths were taken using a steel measuring tape. Due to the presence of deck logs in certain bays, detailed observations of stoplog checks were not possible. The measurements are preliminary and approximate, with definitions provided for outer and inner lengths in Table 2-1.
Notably from Table 2-1, the inner length of the stoplog checks measured at Bays 1 and 6 — both currently experiencing performance issues — was 164½ inches, which is ½ inch to 1½ inches shorter than those measured at the other bays. Select...
AI summary The document notes discrepancies in the inner length of stoplog checks at Bays 1 and 6, which are experiencing performance issues, compared to other bays. The lengths at these bays are shorter by ½ inch to 1½ inches and consistently range between 164 and 164½ inches across several bays.
4 Contractor OT Cost ($) Tasks Elliot Excavators Elliot's contract was lump sum and included two weekends of work (prime time) as part of their proposal. The cost was not broken out and this allowance of two weekends was used. Sluiceway co...
AI summary The document outlines contractor details and associated costs for various tasks, including sluiceway concrete piers repair, stoplogs cranage, rope access works, and ROV inspection, all conducted during after hours and weekends.
Year Phases July Aug Sep Nov Dec Cost 2024 Project Proposal Fish/bathymetry survey, landowner engagement, initial project proposal for DFO review $ 2,400.00 Studies Land survey and geotechnical investigation $ 28,935.00 Preliminary Enginee...
AI summary The document outlines a project timeline and associated costs for a project proposal, including phases such as surveys, studies, and engineering design, with associated financial figures for the years 2024 and 2025.
"Schedule B" Budget Monitor Labour – Part-Time (10 hours per day, 7 days a week, with a total of 70 hours, 8 monitors rotating throughout the week in teams of 4. ITEM DECCRIPTION 2227
AI summary The document outlines a labor monitoring schedule involving part-time monitors working 10 hours per day, 7 days a week, with a total of 70 hours, and 8 monitors rotating in teams of 4.
Table 2-1: Project Deliverables Stage and Phase Deliverables Part A: Environmental Application Support / Stoplog Design Stage 1 – Inception and Feasibility Phase 1 – Data Review and Site Visit • Health and Safety Plan (site visit) Phase 2...
AI summary Table 2-1 outlines project deliverables for different stages and phases, including environmental application support and stoplog design. It details deliverables such as design basis memoranda, conceptual and detailed design drawings, and feasibility reports.
Table 2-2: Milestone Schedule Task Activity Duration (Days) Start Finish Stage 1 - Inception and Feasibility Phase 1 - Data Review and Site Visit January 27, 2025 January 31, 2025 Task 1-1: Review existing drawings January 29, 2025 Task 1-...
AI summary The milestone schedule outlines the timeline for the project's initial stages, including data review, site visits, and the development of the Design Basis Memorandum and design alternatives for NSPI review.
tage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage Stage...
AI summary The text presents a table with stages and activities related to environmental application support and stoplog design, listing hours and fees. The table includes various stages and associated costs, but specific details are not fully visible due to formatting issues.