N-6NSPI (NSUARB) RIR-1 to 13 - Redacted
5 passages
REDACTED 1 (d) The revised costs associated with archaeological assessment are a result of ongoing 10 11 (b) Please confirm that Consulting Services for the project were procured using a 12 competitive RFP/tender process. 13 14 (i) If not...
AI summary The text requests clarifications on cost discrepancies and procurement processes related to a project, including competitive RFP/tender processes, cost breakdowns, and the omission of certain costs in the 2019 ACE Plan Application.
The Bank of Nova Scotia Trade Services Centre 4th Floor, 1 St. Clair Avenue East Toronto, Ontario M4T 1Z3 Tel: 1-888-722-3867 Fax: 416-866-4286 SWIFT: NOSCCATTTPG Irrevocable Standby Letter of Credit No.: OSB62460GWS Beneficiary: Receiver...
AI summary This document outlines an irrevocable standby letter of credit issued by the Bank of Nova Scotia on behalf of Nova Scotia Power Incorporated to Fisheries and Oceans Canada. It guarantees payment of CAD62,000 for the completion of capital projects on the Sheet Harbour Hydro System and Sloane Lake in 2020.
CI 50518 NSUARB IR-12 Attachment 4 Page 9 of 57 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Ruth Falls Dam Refurbishment S 35(2)(b) Fisheries Act Authorization Supporting Information #1 Monitoring Activities personnel. The system will be m...
AI summary The document outlines NS Power's plan for water management during the Ruth Falls Dam refurbishment, including continuous downstream discharge to maintain fish passage and comply with regulatory requirements. The proposed system has been used successfully by the Halifax Regional Municipality, and NS Power intends to seek a variance from ECC for modifications to flow releases.
CI 50518 NSUARB IR-12 Attachment 10 Page 530 of 591 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Estimated cost: Based on our 2016-2018 project in this area, we would estimate the total cost of completing this work to be approx. $125,000 +...
AI summary The text outlines estimated costs for a habitat restoration project, including contractor fees, consultant costs, and NSSA coordination expenses. It also provides the site location and mentions the involvement of local Mi'kmaw community members in monitoring.
The Bank of Nova Scotia Trade Services Centre 4th Floor, 1 St. Clair Avenue East Toronto, Ontario M4T 1Z3 Tel: 1-888-722-3867 Fax: 416-866-4286 SWIFT: NOSCCATTTPG Irrevocable Standby Letter of Credit No.: OSB62460GWS Beneficiary: Receiver...
AI summary This document outlines an irrevocable standby letter of credit issued by The Bank of Nova Scotia on behalf of Nova Scotia Power Incorporated, benefiting Fisheries and Oceans Canada. The letter of credit is for CAD 62,000 and is used to ensure payment for capital projects on the Sheet Harbour Hydro System and Sloane Lake in 2020.
N-9Amended Evidence - Midgard - Redacted
2 passages
Table 19: 2019 ACE Application Costs – Consulting[64](#page-40-2) Description Total Estimate ($) Design $142,281 RFP Support $6,000 Construction Support $17,500 Environmental $4,780 KMKNO Capacity Payments XXXXXXX TOTAL: XXXXXXXX Table 20:...
AI summary The text presents two tables detailing the estimated consulting costs for the 2019 Affordable Clean Energy (ACE) Application and the ATO Application. The tables include line items such as design, environmental studies, and monitoring activities. The ACE table includes a total estimate of XXXXXXXX, while the ATO table has a total estimate of $1,877,234.
DUE DILIGENCE - Experience with the due diligence analysis of a variety of renewable resource projects, including the evaluation and modeling of the revenues and costs associated with mid-life energy projects. - Evaluation of site visit ma...
AI summary The text outlines experience in due diligence for renewable energy projects, including hydroelectric and other mid-life energy projects. It highlights participation in evaluations for clients in Canada, Zambia, and the USA, focusing on technical, economic, and contractual aspects.
98138Board Decision
3 passages
1.1 Project Background [5] In 2015, NS Power engaged Kleinschmidt as a consultant to assess the design adequacy of NS Power's Sheet Harbour Hydro System's water retaining structures. The assessment evaluated the structures' stability under...
AI summary In 2015, NS Power commissioned Kleinschmidt to assess the Sheet Harbour Hydro System's water retaining structures, which led to a 2019 ACE Plan approval for a project addressing deficiencies in the Ruth Falls Dam. The current ATO application requests an increase from the originally approved amount due to increased environmental permitting, extended timelines, and archaeology and Mi'kmaq engagement costs.
3.2 Preferred Refurbishment Option [65] In approving NS Power's 2019 ACE Plan, the Board agreed with NS Power that Option 4 was the preferred and most economic refurbishment alternative for the project. As noted above, NS Power's CEJC expl...
AI summary The Board approved NS Power's 2019 ACE Plan, finding that Option 4 remains the preferred refurbishment option. NS Power did not update its economic analysis due to expected uniform cost increases from FAA and extended timelines, and no other parties challenged this reasoning.
s and external stakeholders. While the Board is encouraged by these efforts, it acknowledges that the Utility has little control over the actions and requirements of those regulators and stakeholders. [69] Additionally, NS Power has alloca...
AI summary NS Power has allocated $500,000 for habitat offsetting costs based on a rate suggested by DFO, but not its own higher estimate. The project faces potential cost increases if the higher rate or larger offset area is required. The FAA status remains unclear, with further consultation needed with the Mi'kmaq of Nova Scotia, leaving the project exposed to cost escalations.