103607Complainant Response re NSPI Extension Request (redacted)
1 passage
Tue, Aug 11, 2026 at 4:21 PM To: Planning Coordinator Central Good afternoon, I appreciate your attention to this matter. While I understand that this is a bit of a pragmatic move to ensure there are no further delays to this project, I do...
AI summary Jefferson Crabtree is informing Nova Scotia Power about delays in a project due to a neighbor's interference and requests flexibility regarding upfront payments for potential rock breaking costs, citing that prior work has not been completed and questioning the necessity of the rock breaking.
103651Complainant Reply to NSPIs Response d. September 21, 2026 (redacted)
1 passage
2. NSP already accepted the electrical permit and payment in May. My electrician submitted the electrical permit documentation to NSP in May. NSP accepted payment and issued the permit. Please see the attached documentation. NSP subsequent...
AI summary The document states that NSP accepted an electrical permit and payment in May but later scheduled installation without checking the building permit or municipal exemption. The author questions why the permit was not identified earlier and what has changed since May.
Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →