HomeMattersM13034
M13034 Open Electricity

NSPI Complaint - Power Pole and Easement Issues - Jefferson Crabtree

Filed 08/12/2026 8 documents

What's happened

Filing Timeline

  • 08 Sep
    Document
    Nova Scotia Power requests complaint held in abeyance pending court order to ensure employee safety during power pole installation for customer Jefferson Crabtree
  • 31 Aug
    Document
    Complainant Jefferson Crabtree files update with NSEB reporting unscheduled pole installation work and escalating neighbour dispute ahead of September 8 deadline
  • 24 Aug
    Document
    Nova Scotia Power requests and receives extension to September 8, 2026 to resolve power pole installation delayed by neighbour easement dispute in M13034
  • 12 Aug
    Correspondence
    NSEB acknowledges Jefferson Crabtree complaint regarding Nova Scotia Power pole and easement issues, directing NSPI to respond by August 26, 2026
  • 11 Aug
    Document
    Jefferson Crabtree files complaint against Nova Scotia Power over three-month delay in power pole installation and service connection

The filings themselves

Documents

Exhibits 2 files
  • C-1 Notice of Complaint (redacted) PDF · 08/11/2026
  • C-2 Complainant Update re Scheduled Work (redacted) PDF · 08/31/2026
Other documents 6 files
  • 103182 Board Acknowledgment Letter (redacted) PDF · 08/12/2026
  • 103318 NSPI Extension Request PDF · 08/24/2026
  • 103320 Board Extension Request Approval (redacted) PDF · 08/24/2026
  • 103321 Appellants Response to NSPI Ext Request (redacted) PDF · 08/24/2026
  • 103322 Appellants Follow Up Response to NSPI Ext Request (redacted) PDF · 08/24/2026
  • 103477 NSPI Second Ext Request (redacted) Processing…