1st Quarter Overview - as of March 31, 2025
1st Quarter Overview - as of March 31, 2025 ACE Plan Reference Submission or Approved Generation C0029691 CT - VJ1 Control System Upgrade 2022 ACE Plan 2022 ACE Plan $ 1,016,225 $ 1,016,225 $ 1,002,085 Approved Transmission C0045132 ECEI -...
AI summary This document provides an overview of capital expenditures approved and deferred in the first quarter of 2025, including projects related to generation, transmission, and distribution. It references the 2022 ACE Plan and includes order numbers for approvals and deferrals.