2026 DSM Cost Recovery Rider (IG M12521) NSPI Responses to IG Information Requests
p. p. 6
2026 DSM Cost Recovery Rider (IG M12521) NSPI Responses to IG Information Requests 1 Request IR-6: 2 3 Reference: N-1, DCRR Application, Appendix A-1, Tab: Data Input – Usage. 4 5 (a) What is the date of the forecast(s) on which the 2026 s...
AI summary The response to Information Gathering (IG) Request IR-6 regarding the 2026 DSM Cost Recovery Rider confirms that the forecast used is the most recent one prepared in September 2025. A table is referenced for detailed load and revenue data for various industrial classes.