Topic/Matter Intersection

Topic:"Generation Grid Resources" in M12417

Matter: Nova Scotia Power Inc. - CI C0071528 – FLISR Implementation – $4,638,245
5 passages 3 documents

Generation Grid Resources across all matters →

N-1Application - CI C0071528 - FLISR Implementation - Redacted 3 passages
nclusions p. p. 8
as projects with a primary purpose that is integral to the effective operation of a system, These collective capabilities provide a service that is made up of nodes and vectors into a grid or system." Using this definition, power transmiss...

AI summary This text discusses the definition and characteristics of power transmission projects, emphasizing their role as vectors in the grid system, the challenges in defining their scope, and the similarities in estimating principles between transmission and distribution projects.

The table below provides a scope summary and pricing for S&C's services. p. p. 31
The table below provides a scope summary and pricing for S&C's services. SERVICES Item Description Price 4 Overcurrent Protection Device Coordination Study S&C Electric Company (S&C) will perform Overcurrent Protection Device Coordination...

AI summary The table outlines a scope summary and pricing for S&C Electric Company's Overcurrent Protection Device Coordination (OPDC) study for the Wreck Cove Feeder of Nova Scotia Power. The study involves evaluating and setting overcurrent protection devices to ensure selective coordination and equipment protection.

REDACTED CI C0071528 Attachment 2 Page 9 of 21 REDACTED (CONFIDENTIAL INFORMATION REMOVED) p. pp. 35-36
REDACTED CI C0071528 Attachment 2 Page 9 of 21 REDACTED (CONFIDENTIAL INFORMATION REMOVED) S&C Electric Company Proposal No. BD-13736 Nova Scotia Power, Incorporated – Wreck Cove Feeder

AI summary The document references a proposal by S&C Electric Company (Proposal No. BD-13736) related to Nova Scotia Power, Incorporated’s Wreck Cove Feeder. This appears to be part of a regulatory proceeding, though specific details are redacted.

N-2NSPI (NSEB) RIR 1 to 9 1 passage
Segmentation FLISR Scheme – 11S-411 Sydney p. pp. 57-58
Segmentation FLISR Scheme – 11S-411 Sydney

AI summary The document discusses the Segmentation FLISR Scheme – 11S-411 Sydney, which involves fault location, isolation, and service restoration in the distribution system. It includes a reference to a picture on page 58, likely depicting a diagram or visual representation of the scheme.

100262Board Decision Letter 1 passage
M12417 – Nova Scotia Power Inc. - CI C0071528 – FLISR Implementation – $4,638,245 p. p. 0
137H-414. However, for analysis purposes, the Board considered the maximum performance values for the past five years (year-to-date). In that case, the following feeders do not meet the 2024 targets: - Feeder 11S-411 (both CKAIFI and CKAID...

AI summary The document discusses the performance of specific feeders in Nova Scotia Power's grid, noting that some do not meet 2024 reliability targets. NS Power is implementing FLISR technology in high-density urban areas to improve reliability and address challenges such as fault location and outage restoration. The feeders in remote areas face additional challenges due to their radial design and location.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →