M12417 Closed Electricity

Nova Scotia Power Inc. - CI C0071528 – FLISR Implementation – $4,638,245

Filed 08/05/2025 14 documents

The filings themselves

Documents

Key documents 1 file
  • 100262 Board Decision Letter PDF · 12/10/2025
Exhibits 4 files
  • N-1 Application - CI C0071528 - FLISR Implementation - Redacted PDF · 08/05/2025
  • N-1(C) Application - CI C0071528 - FLISR Implementation - Confidential PDF · 08/05/2025
  • N-2 NSPI (NSEB) RIR 1 to 9 PDF · 10/02/2025
  • N-3 NSPI (NSEB) RIR 10 - 12 PDF · 11/24/2025
Other documents 9 files
  • 98845 Second Quarter 2025 Capital Items - NSPI PDF · 08/05/2025
  • 99128 NSEB (NSPI) IR 1 to 9 PDF · 08/27/2025
  • 99370 Letter NSPI re: Extension Request PDF · 09/17/2025
  • 99371 Board Letter re: Extension approved PDF · 09/17/2025
  • 99549 Letter NSPI re: RIRs PDF · 10/02/2025
  • 99861 NSEB (NSPI) RIR 10 to 12 PDF · 10/31/2025
  • 100066 Letter NSPI re: RIRs PDF · 11/24/2025
  • 100262 Board Decision Letter PDF · 12/10/2025
  • 100418 Board letter re: Clarification PDF · 12/22/2025

What's discussed — click to drill in

Topics

Grid Modernization
40 passages across 6 documents
Distribution
29 passages across 6 documents
System Reliability
24 passages across 7 documents
Infrastructure Planning
14 passages across 7 documents
Capital Expenditures
13 passages across 5 documents
Regulatory Approval Processes
13 passages across 10 documents
Rates And Money
12 passages across 1 documents
Contract Terms
10 passages across 1 documents
Planned Outage
9 passages across 3 documents
Distribution Planning
7 passages across 3 documents
Unplanned Outage
7 passages across 3 documents
Confidentiality
6 passages across 2 documents
Harmonized Sales Tax
6 passages across 1 documents
Generation Grid Resources
5 passages across 3 documents
Compliance Legislation
4 passages across 1 documents
Generator Interconnection
4 passages across 1 documents
Operating Expenses
4 passages across 3 documents
2025 Ace Plan
3 passages across 2 documents
Cost Considerations
3 passages across 2 documents
Performance Monitoring
3 passages across 3 documents
Regulatory Oversight
3 passages across 2 documents
Renewable Energy
3 passages across 1 documents
Taxes
3 passages across 1 documents
Asset Management
2 passages across 2 documents
Cybersecurity
2 passages across 2 documents
Emergency Response
2 passages across 2 documents
Energy Efficiency Financing
2 passages across 1 documents
Legal Procedures
2 passages across 1 documents
Standardized Filing
2 passages across 1 documents
Accounting Standards
1 passages across 1 documents
Affordability
1 passages across 1 documents
Boards Regulatory Rules
1 passages across 1 documents
Cost Deferral
1 passages across 1 documents
Cost Effectiveness
1 passages across 1 documents
Cost To Customer
1 passages across 1 documents
Customer Service
1 passages across 1 documents
Depreciation Amortization
1 passages across 1 documents
Energy Efficiency
1 passages across 1 documents
Energy Efficiency Budgets
1 passages across 1 documents
Energy Efficiency Resource Assessment Model
1 passages across 1 documents
Energy Management Information Systems
1 passages across 1 documents
Energy Storage
1 passages across 1 documents
Financing Alternatives
1 passages across 1 documents
Legal Costs
1 passages across 1 documents
Power Infrastructure
1 passages across 1 documents
Project Schedule
1 passages across 1 documents
Rate Base
1 passages across 1 documents
Rate Design
1 passages across 1 documents
Regulatory Compliance
1 passages across 1 documents
Stakeholder Engagement
1 passages across 1 documents
Standard Of Review
1 passages across 1 documents
Transmission Planning
1 passages across 1 documents