NON-CONFIDENTIAL 1 Request IR-1: 27 (d) NS Power submitted its application at the earliest feasible time. The November 2024 28 inspection identified that the stoplogs required replacement. At that time, NS Power and 29 its consultant began...
AI summary NS Power submitted an application for a project following an inspection in November 2024 that identified the need to replace stoplogs. Preliminary engineering and planning were undertaken to prepare the application for the NSEB.