Plant/Unit: TUFTS COVE-1 Siemens Energy Limited provided technical field advisors required to complete the work scope. The work schedule was two 10-hour shifts per day, 6 days a week. This schedule was maintained throughout the outage. The...
AI summary The outage at TUFTS COVE-1 involved Siemens Energy Limited providing technical field advisors, with labor provided by Nova Scotia Power and Fundy millwrights. The work schedule was two 10-hour shifts per day, six days a week, maintained throughout the outage.