Nova Scotia Power inc. - CI C0080150 – TUC1 HP Turbine Refurbishment - $2,527,606 (U&U)2026 Q1 Capital Reports

Filed 05/04/2026 5 documents

What's happened

Filing Timeline

  • 29 May
    Decision
    NSEB approved Nova Scotia Power's $2,527,606 Unforeseen and Unbudgeted capital expenditure for the Tufts Cove Unit 1 HP Turbine Refurbishment completed in December 2025.
  • 04 May
    Document
    Nova Scotia Power seeks NSEB approval for $2.53M unforeseen capital expenditure to refurbish Tufts Cove Unit 1's high-pressure turbine, which was completed in December 2025 to eliminate chronic vibration faults.

The filings themselves

Documents

Key documents 1 file
  • 102189 Decision Letter PDF · 05/29/2026
Exhibits 2 files
  • N-1 CI C0080150 – TUC1 HP Turbine Refurbishment - $2,527,606 - Redacted PDF · 05/04/2026
  • N-1(C) CI C0080150 – TUC1 HP Turbine Refurbishment - $2,527,606 - Confidential PDF · 05/04/2026
Other documents 2 files
  • 101857 Letter NSPI re:First Quarter 2026 Capital Items PDF · 05/04/2026
  • 102189 Decision Letter PDF · 05/29/2026