Why do this project now? The project was undertaken due to the ongoing and unpredictable nature of the vibration events and their increasing risk of impacting unit availability. Continued operation without corrective action heightened the...
AI summary The project was initiated to address ongoing vibration issues in TUC1's HP turbine, which risked unit availability and potential secondary damage. Proactive remediation during a planned maintenance outage minimized these risks and avoided forced derates or trips during critical operations.