Why do this project?
p. p. 8
Why do this project? The Seton Ridge development will include 2,800 multi-unit and 164 single-family dwellings and associated commercial space, with approximately 25% of customers requiring 400A service. The resulting load demand is foreca...
AI summary The Seton Ridge development requires 12 MVA load capacity, exceeding existing infrastructure. NS Power proposes an underground ductbank installation to support growth, enhance reliability, and align with long-term 12.5 kV to 25 kV conversion plans, reducing outages and enabling future feeder expansion.