Topic/Matter Intersection

Topic:"Hearing Procedures" in M12795

Matter: Town of Berwick Electric Commission - Factorydale Hydropower Plant Refurbishment - $6,000,000
5 passages 4 documents

Hearing Procedures across all matters →

B-2Proof of Advertisement 2 passages
Nova Scotia Energy Board - Notice of Paper Hearing p. p. 0
Nova Scotia Energy Board - Notice of Paper Hearing Paper Hearing Bervick Electric Commission (BEC) applied to the Nova Scotia Energy Board on Ard 18, 2026, for approved of a Capital Work Order for the Factorydiae Hydropower Plant Refurblis...

AI summary Bervick Electric Commission (BEC) seeks approval for a $6,000,000 Capital Work Order for the Factorydiae Hydropower Plant Refurbishment. The Nova Scotia Energy Board will hold a public hearing to consider the application, inviting stakeholder participation.

NOVA SCOTIA ENERGY BOARD NOTICE OF PAPER HEARING p. p. 1
NOVA SCOTIA ENERGY BOARD NOTICE OF PAPER HEARING Berwick Electric Commission (BEC) applied to the Nova Scotia Energy Board on April 8, 2026, for approval of a Capital Work Order for the Factorydale Hydropower Plant Refurbishment in the amo...

AI summary Berwick Electric Commission (BEC) seeks approval for a $6,000,000 Capital Work Order to refurbish the Factorydale Hydropower Plant. The Nova Scotia Energy Board will conduct a public paper hearing, allowing written comments and formal intervenor participation by specified deadlines.

101644Hearing Order 1 passage
HEARING ORDER
HEARING ORDER BEFORE : Richard J. Melanson, LL.B., Chair Marc L. Dunning, P.Eng., LL.B., Member Darlene Willcott, LL.B., Member Berwick Electric Commission (BEC) applied to the Nova Scotia Energy Board on April 8, 2026, for approval of a C...

AI summary The Nova Scotia Energy Board has ordered a paper hearing for Berwick Electric Commission's (BEC) $6 million Capital Work Order application for the Factorydale Hydropower Plant Refurbishment. A timetable for interventions, submissions, and evidence is set, with potential conversion to an oral hearing if needed. Regulatory rules and advertising requirements are specified.

101644Hearing Order 1 passage
HEARING ORDER
HEARING ORDER BEFORE : Richard J. Melanson, LL.B., Chair Marc L. Dunning, P.Eng., LL.B., Member Darlene Willcott, LL.B., Member Berwick Electric Commission (BEC) applied to the Nova Scotia Energy Board on April 8, 2026, for approval of a C...

AI summary Berwick Electric Commission (BEC) seeks approval for a $6M Capital Work Order for the Factorydale Hydropower Plant Refurbishment. The Nova Scotia Energy Board will conduct a paper hearing with a structured timetable, including intervention notices, information requests, and submissions deadlines. The Board Regulatory Rules apply, and BEC must advertise the hearing in specified media.

101645Notice of Paper Hearing 1 passage
NOTICE OF PAPER HEARING p. p. 0
NOTICE OF PAPER HEARING _____________________________________________________________________________ Berwick Electric Commission (BEC) applied to the Nova Scotia Energy Board on April 8, 2026, for approval of a Capital Work Order for the...

AI summary Berwick Electric Commission (BEC) seeks approval for a $6M Capital Work Order to refurbish the Factorydale Hydropower Plant. The Nova Scotia Energy Board will conduct a public paper hearing, accepting written comments until July 16, 2026, and allowing intervenor applications by May 7, 2026. Full details are available under Matter No. M12795 on the Board's website.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →