DESCRIPTION:
p. p. 1
DESCRIPTION: This project is for the rewind of the 6P mobile transformer. 6P experienced two faults during installation at 108H Burnside Substation in April 2017, resulting in damage to the low voltage winding. After the failure, the trans...
AI summary This document describes a project to rewind the 6P mobile transformer, which experienced faults during installation in 2017. The transformer, manufactured in 1991, is a critical asset for providing contingency during unplanned outages and maintenance. It was sent for evaluation after damage to the low voltage winding occurred.