LEU Response to IR-5 - a) i) No RFP was issued as LEU has a contract with NSP for field work. NSP could not complete the work due to their existing workload, and as such the authorized contractors needed to be engaged. Of the two authorize...
AI summary The LEU responded to IR-5 by explaining that no RFP was issued as NSP has a contract for field work, and K-Line was selected due to availability. Transformers will be procured through NSP. In response to IR-6, the work is expected to be completed by December 2026. IR-7 requests information on whether an oil test was conducted on the transformers for PCB content.