HomeRate BaseM12595Evidence
Topic/Matter Intersection

Topic:"Rate Base" in M12595

Matter: Nova Scotia Power Inc. - CI 51956 – 6P Mobile Substation Rewind U&U $635,776 (FIN)
1 passage 1 document

Rate Base across all matters →

N-1Application 1 passage
Reason for Variance p. p. 1
Reason for Variance The decrease of $880,345 from the approved budget of $1,516,121 is primarily due to the results of the RFP for the materials and contracts portion of the rewind and refurbishment coming in approximately 60% lower than t...

AI summary The decrease of $880,345 from the approved budget is due to the RFP results for materials and contracts being 60% lower than the original estimate. NS Power acknowledges the delay and outlines efforts to improve timely submissions and reporting.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →