Matter: Nova Scotia Power Inc. - CI C0067183 – TUC Wharf Access Bridge Replacement - $2,426,669 (U&U)
2 passages 2 documents

Rates And Money across all matters →

N-1Application - CI C0067183 - TUC Wharf Access Bridge Replacement - Redacted 1 passage
Fees and Deliverables p. p. 88
Fees and Deliverables Harbourside propose to provide the detailed design drawings for NSPI review at 90% completion, then incorporate any comments and issue sealed construction drawings. The drawings will include comments required for the...

AI summary Harbourside Engineering proposes to provide detailed design drawings for NSPI review at 90% completion, incorporating comments before issuing sealed construction drawings. The project will be completed for a lump sum, excluding HST. Thomas McNutt, a senior structural engineer, is the contact person for the proposal.

99919Board Decision Letter 1 passage
Section 1 p. pp. 0-1
November 7, 2025 [[email protected]](mailto:[email protected]) Lana Myatt Senior Regulatory Analyst Nova Scotia Power Inc. 1223 Lower Water Street PO Box 910 Halifax, NS B3J 3S8 Dear Ms. Myatt: M12420 – Nova Scotia Power Inc. (NS P...

AI summary NS Power has applied for approval to replace the deteriorated Tufts Cove Wharf Access Bridge, which is essential for fuel transfer to several generating stations. The project, costing $2,426,669, was approved by the Board after assessing structural concerns and selecting a cost-effective steel and timber design.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →