Matter: Nova Scotia Power Inc. - CI 51956 – 6P Mobile Substation Rewind U&U $635,776 (FIN)
4 passages 4 documents

Rates And Money across all matters →

N-1Application 1 passage
Approved $1,516,121 Current Submission $635,776 Variance (880,345) p. p. 1
Approved $1,516,121 Current Submission $635,776 Variance (880,345) Submitted on behalf of NOVA SCOTIA POWER INCORPORATED Approved on behalf of NOVA SCOTIA ENERGY BOARD Authorized Signatory DATE DATE Dave Pickles November 27, 2025 Chief Ope...

AI summary The document shows an approved amount of $1,516,121 for a submission by Nova Scotia Power Incorporated, with a current submission of $635,776 and a variance of ($880,345). The submission was authorized by Dave Pickles, Chief Operating Officer of Nova Scotia Power Incorporated, on November 27, 2025.

100740Board Decision Letter 1 passage
Section 6 p. p. 1
Approved $1,516,121 Current Submission $635,776 Variance (880,345) Submitted on behalf of NOVA SCOTIA POWER INCORPORATED Approved on behalf of NOVA SCOTIA ENERGY BOARD DATE Authorized Signatory Dave Pickles Chief Operating Officer November...

AI summary The document shows a submission and approval of financial figures related to a proceeding. Nova Scotia Power Inc. submitted a current submission of $635,776, which was approved for $1,516,121, resulting in a variance of ($880,345). The submission was authorized by Dave Pickles, Chief Operating Officer of Nova Scotia Power Inc., and approved by the Nova Scotia Energy Board on January 27, 2026.

100141Letter NSPI re: Capital Items Filed Outside the Quarter Package 1 passage
Commercial Information p. p. 0
Commercial Information Items 1-2: Partial confidentiality was applied to costs associated with materials, contracts, consulting, first nations commitments, and freight details provided in the capital work order(s). To protect value for cus...

AI summary NS Power applies partial confidentiality to certain costs in capital work orders to protect customer value and prevent competitive disadvantages. The disclosure of supplier pricing and arrangements could lead to higher costs for customers and reduce competition. NS Power argues that maintaining confidentiality helps secure the best terms for acquiring services and equipment.

100740Board Decision Letter 1 passage
Section 6 p. p. 1
Approved $1,516,121 Current Submission $635,776 Variance (880,345) Submitted on behalf of NOVA SCOTIA POWER INCORPORATED Approved on behalf of NOVA SCOTIA ENERGY BOARD DATE Authorized Signatory Dave Pickles Chief Operating Officer November...

AI summary The document shows a submitted amount of $635,776 on behalf of Nova Scotia Power Incorporated, which was approved for $1,516,121 by the Nova Scotia Energy Board. The variance between the submitted and approved amounts is $880,345. The document was signed by Dave Pickles, Chief Operating Officer, on November 27, 2025, and approved by the Energy Board on January 27, 2026.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →