Topic/Matter Intersection

Topic:"Rates And Money" in M13050

Matter: Town of Mahone Bay Electric Utility - Edgewater Project $2,650,000
2 passages 2 documents

Rates And Money across all matters →

M-1Application for capital project 1 passage
Section 2
g transmission infrastructure owned by Nova Scotia Power Inc. – at reduced cost. Assessed against future customer growth in the impacted area, the cost of the infrastructure improvement is reasonable. In addition to improving service for e...

AI summary The Town of Mahone Bay requests the Board to approve a project to upgrade transmission infrastructure owned by Nova Scotia Power Inc. at a reduced cost. The project will support future customer growth and is expected to have a 5.56% impact on customer rates, which may be offset over time by new customer growth.

103418NSEB (ToMB) IR-1 to IR-21 1 passage
Section 13
- for the Utility. - Request IR-15: - What is the current balance in the Utility's Accumulated Surplus account? - Request IR-16: - When was the Utility's most recent rate application to the Board? - Request IR-17: - When does the Utility e...

AI summary The text contains a series of requests directed at the Utility regarding its financial status, rate applications, revenue requirements, cost assessments, borrowing plans, and grant applications related to a proposed infrastructure project.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →