From: [email protected] Sent: April 15, 2026 3:38 PM Cc: Customer Relations < [email protected]> Subject: DRO Final Written Decision re Wint Porter re Nova Scotia Power Bill Dispute \ \ Exercise Caution - This is an...

AI summary A final written decision from the DRO regarding a bill dispute between Wint Porter and Nova Scotia Power is communicated via email. The message serves as an official notification of the resolution.

P-4NSPI Response to Appeal (redacted) 1 passage
Section 4 p. p. 0
vided its position to DRO, stating the following: - […] Meter connections to our billing system have been restored and customer billing is returning to normal. - NS Power confirms that the customer's meter reads for July, September and Nov...

AI summary NS Power disputes a customer's claim regarding estimated meter readings and billing adjustments, asserting that estimated bills were corrected with a $594.81 credit and subsequent in-person meter reads reconciled actual usage. The DRO's Final Written Decision (April 15, 2026) upheld NS Power's billing as compliant with Regulation 5.1.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →