HomeRenewable EnergyM03097Evidence
Topic/Matter Intersection

Topic:"Renewable Energy" in M03097

Matter: CI# 28098 - P-128.07 - NSPI WO -  Authority to Overspend the Tufts Cove 6 Waste Heat Recovery Project - $8,699,864Approximate value for approval of $8.5 million.
16 passages 6 documents

Renewable Energy across all matters →

N-1Application 5/3/2010 3 passages
Project Benefit Update p. p. 0
Project Benefit Update 2 3 While not analyzed yet, the recently announced Provincial Electricity Plan indicating an 4 of increased renewable energy target 40% by 2020 will likely require additional intermittent 5 resources which will furth...

AI summary The document discusses the potential impact of the Provincial Electricity Plan's increased renewable energy target of 40% by 2020 on the need for additional intermittent resources. It also references the Tufts Cove 6 project, which provides low carbon dioxide emitting generation to help the company meet provincial C02 emission limits. The text also references the UARB's approval process and a past decision regarding an Authority to Overspend (ATO) application.

Consistent with this directive, NSPI has sought to compile the necessary cost information and economic analysis support to allow the Board to approve the enclosed ATO. The Company p. p. 0
Consistent with this directive, NSPI has sought to compile the necessary cost information and economic analysis support to allow the Board to approve the enclosed ATO. The Company respectfully suggests the Board seek written input from the...

AI summary NSPI is requesting the Board to seek written input from original participants in CI 28098 regarding the Tufts Cove 6 project. The project's justification remains unchanged since 2008, and it is expected to deliver significant savings, system stability, support for renewable energy, and environmental benefits. Cost increases are attributed to unforeseen cost drivers.

Assumptions: p. p. 12
Assumptions: - 5%DSM & Rnew Plan - TUC 6 No Duct Firing - In-service Dec/2010 - Capital Cost $78M ($2010)

AI summary The text outlines assumptions related to a 5% DSM & Renewable Plan, a TUC 6 No Duct Firing project with a capital cost of $78M (2010 value), and an in-service date of December 2010.

N-3Redacted NSPI (NSUARB) IR-1 to IR-20 7/16/2010 7 passages
4 p. p. 7
4 NPV Benefit NPV Benefit Total Project TUC 6 without TUC 6 with NPV Benefit Duct-Firing Duct-Firing $M Vs Vs No TUC 6 TUC 6 without (Strategist) DF $M $M May 2008 Filing 43.84 31.60 75.44 2010 Revision 37.70 29.49 67.19 Analysis using 200...

AI summary The text presents a table comparing NPV benefits of different scenarios related to the TUC 6 duct-firing project, including various filings and revisions, and the impact of the NPPH Biomass Project on these benefits.

Section 8 p. p. 7
6 7 8 9 10 11 NSPI has completed an economic analysis of system costs with and without Tufts Cove 6, with duct-firing and without duct-firing. The analysis utilizes two cases, Port Hawkesbury (PH) Biomass Project Base Case Plan A and High...

AI summary NSPI conducted an economic analysis of the Tufts Cove 6 project, considering scenarios with and without duct-firing. The analysis uses two cases based on the 2009 IRP Update assumptions and shows that the net present value remains positive with duct-firing.

NON-CONFIDENTIAL p. pp. 7-9
NON-CONFIDENTIAL 1 filing is that the project economics are no longer driven primarily by the 2 combined cycle conversion. 3 4 This change is the result of the reduced load assumed in the Base Load World. 5 Under this assumption, Tufts Cov...

AI summary The project economics have shifted due to reduced load assumptions in the Base Load World, leading to lower forecast dispatch for Tufts Cove Units 4 and 5. This has resulted in a negative NPV for the combined cycle conversion without duct-firing. The analysis assumes traditional NSPI load growth levels and notes that the economic analysis lacks the same parameter sensitivities as the 2009 IRP, particularly regarding potential lower natural gas prices.

NON-CONFIDENTIAL p. p. 7
NON-CONFIDENTIAL 1 2 The implications of this are that the analysis, in particular the Base Case analysis, 3 is likely conservative (i.e. benefits are likely understated) for the following 4 reasons: 5 6  The Tufts Cove Units are marginal...

AI summary The text discusses the implications of the Base Case analysis, suggesting it may be conservative due to factors such as the marginal cost nature of Tufts Cove Units, potential benefits from wind development, and continued savings from duct-firing. It emphasizes the value of increased natural gas-fired generation flexibility and favorable emissions profile despite higher capital costs.

NPV Benefit of TUC 6 No Duct Firing (Base Case Plan A with NPPH Biomass Project) 2009 IRP Update Assumptions with NPPH Biomass Project p. p. 7
NPV Benefit of TUC 6 No Duct Firing (Base Case Plan A with NPPH Biomass Project) 2009 IRP Update Assumptions with NPPH Biomass Project Capital Costs: osts: Operating Costs: Costs: Capital Cost $78M Total Base Case NPPH Biomass Base Case NP...

AI summary The document presents a Net Present Value (NPV) analysis of the TUC 6 No Duct Firing project in conjunction with the NPPH Biomass Project, comparing capital and operating costs over time. It includes cumulative costs and PV benefits, with a discount rate of 6.81%, and highlights the project's in-service date as December 2012.

2.2 BURIED PIPING p. pp. 160-161
2.2 BURIED PIPING - Storm Pipe PVC CAN/CSA- B182.2-M95 SDR 35 and Reinforced Circular Concrete Pipe to CAN/CSA-A257, ASTM C76 designed for flexible rubber joints to ASTM C443, CAN/CSA-A257 - Water Pipe AWWA C110 Ductile Iron and Fittings t...

AI summary The text outlines specifications for various types of buried piping systems, including storm, water, intake, and outfall pipes, along with materials and standards they must comply with. It includes references to specific standards and organizations involved in the project.

Preamble p. pp. 168-212
Water reducing admixtures, Super plasticizers (water reducing high range admixture), and accelerating admixtures shall meet the requirements of CAN 3-A266. Calcium chloride and any admixture containing calcium chloride shall not be used. R...

AI summary The text outlines specifications for concrete construction, including requirements for admixtures, reinforcing bars, concrete floor thickness, formwork design, expansion joints, crack control joints, and finished floor elevations. It references CSA and other standards for compliance.

N-7NSPI Reply Submission 8/6/2010 1 passage
Conclusion p. p. 0
Conclusion The evidence available to the Board in this application demonstrates that the steps taken by NSPI during planning and construction of this Project were reasonable, prudent and led to significant preservation of value for NSPI cu...

AI summary The evidence shows that NSPI's actions during the planning and construction of the Project were reasonable and prudent, benefiting customers. The ATO application for TUC6 is deemed the best economic option, with cost increases due to unforeseen factors. NSPI requests approval of the ATO for CI 28098.

05797Board Decision 2 passages
Preamble p. p. 0
[1 ] On May 3, 2010, Nova Scotia Power Incorporated ("NSPI", the "Utility") submitted a request for Approval to Overspend ("ATO") to the Nova Scotia Utility and Review Board (the "Board") for the Tufts Cove 6 ("TUC6") Waste Heat Recovery P...

AI summary On May 3, 2010, NSPI requested an ATO from the Board for the TUC6 Waste Heat Recovery Project, which involves recovering waste heat from two combustion turbines to generate additional electricity. The request amount is $8,699,864, bringing the total project cost to $92,996,628.

Counsel: p. p. 0
alue in the early years and a higher value to customers - the benefit being that, regardless of how it's modeled in the IRP, that benefit will flow through the fuel adjustment mechanism for customers. ... 1 think there are other aspects, o...

AI summary The discussion centers on the Tufts Cove 6 project and its expected performance, particularly its efficiency and capacity factor compared to the reference plan. The speaker argues that the plant will provide significant economic benefits and flexibility, especially with the current natural gas prices and the integration of wind energy.

04698NPB IRs to NSPI (IR-1 to IR-4) 6/30/2010 1 passage
IN THE MATTER OF AN APPLICATION For Authority to Overspend (ATO) - TUC6 Waste Heat Recovery Project CI#28098 - (P-128.07)
IN THE MATTER OF AN APPLICATION For Authority to Overspend (ATO) - TUC6 Waste Heat Recovery Project CI#28098 - (P-128.07) NewPage Port Hawkesbury Corp. and Bowater Mersey Paper Company Ltd. ("NPB") Information Requests to Nova Scotia Power...

AI summary The document outlines information requests made by NewPage Port Hawkesbury Corp. and Bowater Mersey Paper Company Ltd. to Nova Scotia Power Inc. regarding the TUC6 Waste Heat Recovery Project and an application for Authority to Overspend (ATO).

05797Board Decision 2 passages
Preamble p. p. 0
[1 ] On May 3, 2010, Nova Scotia Power Incorporated ("NSPI", the "Utility") submitted a request for Approval to Overspend ("ATO") to the Nova Scotia Utility and Review Board (the "Board") for the Tufts Cove 6 ("TUC6") Waste Heat Recovery P...

AI summary On May 3, 2010, Nova Scotia Power Incorporated submitted a request for an Authority to Overspend for the Tufts Cove 6 Waste Heat Recovery Project to the Nova Scotia Utility and Review Board. The project involves recovering waste heat from two combustion turbines to generate additional electricity, with a total project cost of approximately $93 million.

Counsel: p. p. 0
alue in the early years and a higher value to customers - the benefit being that, regardless of how it's modeled in the IRP, that benefit will flow through the fuel adjustment mechanism for customers. ... 1 think there are other aspects, o...

AI summary The discussion highlights the expected benefits of the Tufts Cove 6 project, including its efficiency and ability to provide economic benefits to customers. It emphasizes the importance of looking at actual expected performance over potential future scenarios, particularly in light of current natural gas prices and the project's flexibility with wind energy on the system.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →