Matter: CI# 39623 - P-510 - NSPI WO - LIN-U&U CW Pump Refurbishment $381,736
1 passage 1 document

Renewable Energy across all matters →

N-1Non-Confidential Work Order 7/30/2010 1 passage
Section 3 p. p. 1
Parent CI Number Cost Centre 305 - 305-Lingan 3&4 Prod.Unit Budget Version - 201007/05 Forecast Forecast Start 08/18/2010 Operational 08/30/2010 Final Cost 09/18/2010 2010 $381,736.22 Total: $381,736.22 Original Cost: $0.00 The Unit 3A pum...

AI summary In March 2010, the Unit 3A pump failed due to a broken shaft caused by misalignment, leading to damage to bearings and surfaces. Refurbishment included replacing the shaft, adding a bearing to prevent future misalignment, and resurfacing corroded components to improve reliability.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →