It is of concern to the Board that the under-scoping of this project was because the nondestructive testing (NOT) did not detect the full extent of the required work. NSPI may want to consider reviewing its NOT protocols to see if the accu...
AI summary The Board notes that the under-scoping of a project was due to nondestructive testing (NOT) protocols not detecting the full extent of required work. It approves an increase of $1,157,09 in the cost of the Work Order, as the over-expenditure is deemed warranted.