N-1Application - Redacted
86 passages
bility. These targeted reliability projects include vegetation 26 management, storm hardening and reliability upgrades, targeted device replacements, and 27 grid modernization. 28 Date: December 12, 2025 Page 8 of 782 REDACTED REDACTED (CO...
AI summary The 2026 ACE Plan focuses on safety compliance, environmental compliance, and aligning with the coal phase-out and renewable energy goals. It includes projects such as hydro dam safety upgrades, PCB remediation, and grid modernization, and addresses directives from the 2025 ACE Plan Decision.
1 5. The Board directs NS Power to provide an update on the Centre for Energy Advancement 2 through Technological Innovation (CEATI) Grid Resiliency working group in the 2026 3 ACE Plan. 6 Please refer to Section 11.1.4. 4 6. The Board dir...
AI summary The Board has directed NS Power to provide updates and analyses related to several projects and plans, including the Centre for Energy Advancement through Technological Innovation (CEATI) Grid Resiliency working group, pole upgrades, The Path to 2030, and the Mersey Hydro System Redevelopment Project, as part of the 2026 ACE Plan.
MacDonald Dam Access Improvements 963,078 1,547,398 This project is for the construction of an access walkway along the top of the spillway to a low level sluiceway gate for the Hydro Operations team to be able to adjust downstream flow re...
AI summary The document outlines several infrastructure projects related to hydro operations and environmental improvements. These include constructing an access walkway at the MacDonald Dam, building a fish passage at the Tusket Powerhouse, replacing a rubber dam at Lumsden, and decommissioning the Annapolis Tidal Generating Station.
CI# Project Title 2026 Budget ($) Project Total ($) and intermediate pressure steam from the boiler to produce power through the generator. C0082195 LIN2 2025/26 Capacity Requirement 299,478 3,162,203 This project is for the component refu...
AI summary The document outlines several infrastructure and maintenance projects across Nova Scotia's energy sector, including asset refurbishment, replacement of equipment, and system upgrades to ensure operational reliability and compliance with environmental regulations.
1,102,575 1,353,592 This project is for refurbishment of priority areas of the roof at the Sydney Coal Railway Transportation & Rail Maintenance Centre (Rail Centre). Total New Steam Spending for Subsequent Approval 10,402,603 24,560,654 T...
AI summary The text outlines various capital expenditure projects in Nova Scotia, including roof refurbishment, synchronous condensers, transmission tower rerouting, and network upgrades for wind farms. These projects aim to enhance infrastructure and support renewable energy integration.
D REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan CONFIDENTIAL (Attachments Only) 1 6.0 GENERATION 2 3 Generation capital includes replacements, refurbishments and additions to NS Power’s Thermal, 4 Hydro, Wind, Combustion Turbin...
AI summary The 2026 ACE Plan discusses NS Power's capital investment in generation, highlighting increases due to major thermal outages and hydro dam safety projects, aligning with the updated unit missions of the legacy thermal fleet as outlined in the 10 Year System Outlook filing.
1 using the Asset Management Mechanism described in Section 3.0, which enables consistent, risk- 2 informed prioritization across the fleet. Investments are selected to maintain safety, reliability, and 3 affordability, with consideration...
AI summary The text outlines NS Power's approach to asset management, emphasizing risk-informed prioritization, safety, reliability, and affordability. It highlights the transition of thermal generation assets toward retirement or fuel conversion by 2030, in line with the Province’s Clean Power Plan, and discusses capital investment plans for both thermal and renewable generation in 2026.
Right-of-Way Widening 128.9 ECEI 7.2 3 3.3 4 5 Transmission investment is guided by NS Power’s Asset Management mechanism and the Capital 6 Expenditure Justification Criteria (CEJC). Asset condition and criticality are evaluated using the...
AI summary The document outlines NS Power’s transmission investment strategy, guided by its Asset Management mechanism and Capital Expenditure Justification Criteria (CEJC). It emphasizes reliability, customer growth, and compliance with environmental obligations, including the Clean Power Plan, which aims for 80% renewable electricity by 2030. Investments in the Eastern Clean Energy Initiative (ECEI) and battery storage are highlighted.
404,118 58,444 462,562 Total Distribution Right-of-Way Widening 13,223,182 Note: Totals may be slightly off due to rounding. 1 2 Pursuant to CI 49611 - New Distribution Rights-of-Way Phase I, submitted to the Board on 3 November 1, 2016, L...
AI summary The document discusses NS Power's response to Post-Tropical Storm Arthur, including recommendations for managing overgrown distribution rights-of-way and the Board's direction to explore innovative financing options. It references a 2016 ACE Plan and a 2015 Board decision.
REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan C0021608 Attachment 1 Page 1 of 34 October 2, 2025 Connor Lebans, P.Eng. Mechanical Engineer – Tufts Cove and CTs Tufts Cove Generating Station 315 Windmill Road Dartmouth...
AI summary This document outlines a condition assessment and conceptual repair options for a section of the SSP wall at the Tufts Cove Generating Station, which has become redundant due to the construction of a new rock revetment. The focus is on the portion of the wall between the new revetment and the Wharf Access Bridge.
NSPI TUFTS COVE SSP WALL REPAIR MARINE OPTION 1 - NEW COMBI WALL PLAN AND ELEVATION
AI summary The text refers to a repair project for the Tufts Cove Steel Sheet Pile (SSP) wall, with an option for a new combi wall plan and elevation under the Marine category.
Drawing No DRAWING NAME: Y:\HALIFAX\DATA\PROJECTS\2022\220322.00 NSPI TUFTS COVE SSP WALL\44 CAD\03 STRUCT\220322.00-MSK02.DWG LAYOUT NAME: OPTION 1 - NEW COMBI WALL PLAN AND ELEVATION PLOT DATE: Thursday, March 9, 2023 11:12:00 AM CAD OPE...
AI summary The text provides a drawing name, layout name, plot date, and CAD operator information for a project related to the Nova Scotia Power Incorporated Tufts Cove Steel Sheet Pile Wall. It includes a title sheet reference and a file path.
NSPI TUFTS COVE SSP WALL REPAIR MARINE OPTION 3 - ELEVATION AND SECTIONS
AI summary The document discusses a repair project for the Tufts Cove SSP wall, focusing on elevation and sections under the marine option. It includes details about the project's scope and structure.
ED units replace in pairs. Repair the loose conduit at the locking nut to the AOL light at the 265’ elevation. please see photo graphs # 3, 37 for further information. Date: December 12, 2025 Page 229 of 782 REDACTED REDACTED (CONFIDENTIAL...
AI summary The text outlines repair tasks for the Tufts Cove Generating Station Unit #2, including replacing damaged caulk sealant, preparing concrete columns for painting, and recommending stack inspections. Contact information for Commonwealth Dynamics Limited is provided for further inquiries.
ur operating units, which provide multiple benefits to NS Power and its customers. This unit, along with all the other combustion turbines, provides essential ancillary services to the system such as: • Peaking capacity – generation used t...
AI summary The text discusses the importance of maintaining four operational units at Burnside, highlighting their role in providing peaking capacity, black start capability, and fast-acting generation to support system reliability, especially with the integration of variable renewable energy sources like wind.
of capital asset criteria and, depending upon requirements, the land will be retained or sold. Month DD, YYYY Page 46 of 54 Date: December 12, 2025 Page 511 of 782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan Appendix...
AI summary Nova Scotia Power Inc. outlines criteria for retaining or releasing abandoned rights-of-way and justifies capital expenditures for hydro, wind, and biomass assets based on safety, legal compliance, economic benefits, reliability, and failure risk. Surplus rights-of-way may be released to property owners.
• When the probability of failure is high enough that: • Making the proposed capital investment reduces the costs compared to con nuing to repair the exis ng asset; • The es mated cost reduc on is of significant magnitude to meet NS Power’...
AI summary NS Power's capital expenditure criteria prioritize economic justification, requiring projects to demonstrate cost reductions compared to repairing existing assets and align with Nova Scotia's Renewable Energy Standards. Thermal asset replacement must balance financial criteria, customer benefits, and renewable energy alternatives.
efit to customers while allowing NS Power to meet its objec ves. The capital planning cycle for any given year typically begins early in the preceding year and concludes at the filing of the ACE Plan. Although the oversight and management...
AI summary Nova Scotia Power Inc. (NS Power) outlines its capital planning process, emphasizing centralized oversight and annual ranking of projects based on health and safety, regulatory compliance, customer reliability (SAIDI, SAIFI), requirement to serve, and economic factors (NPV, ACHI). Projects are reviewed to align with strategic goals and ensure justification.
nings, or aid in the development of business cases where applicable, regarding the efficacy of innova on technology in improving the reliability of the system. Environmental and Other Compliance The Nova Sco a Renewable Energy Standards prov...
AI summary Nova Scotia's Renewable Energy Standards mandate 40% renewable generation from NS Power by 2020, with compliance through technologies like battery storage. Innovation projects must support environmental compliance or provide data for business cases. Customer experience initiatives aim to meet evolving expectations through technology.
the open market. In such instances the property may be acquired if no economically prac cal alterna ve property is available to sa sfy the requirements of the future project in ques on. Land Disposal NS Power can dispose of, lease or grant...
AI summary The document outlines NS Power's policies for land and asset management, including disposal of surplus land, buildings, and rights-of-way, while emphasizing environmental compliance. It also addresses capital planning and expenditure justification criteria for hydro, wind, and biomass assets.
ed na onal standards of stability and flood management capability for exis ng structures, or where accepted criteria of "due diligence" for public and environmental safety cannot be met. • Generator stators will be rewound when there is a...
AI summary NS Power outlines procedures for generator stator maintenance and thermal asset replacement, emphasizing insulation testing, economic justification for capital expenditures, and compliance with Nova Scotia's Renewable Electricity Standards. Decisions prioritize energy value over costs and align with renewable energy mandates.
2026 ACE Plan Appendix E Page 5 of 17 Mersey Hydro Update Non-Confidential
AI summary The 2026 Annual Capital Expenditure (ACE) Plan Appendix E, page 5, details the Mersey Hydro Update, a non-confidential document outlining project progress and financial considerations.
eased from $68.1 million in Appendix G of the 2025 ACE Plan to 26 the current forecast of $79.2 million. NS Power continues to revise the profile of the investment 27 in accordance with its asset management principles to ensure projects ar...
AI summary NS Power is revising the investment profile in the 2026 ACE Plan, increasing the amount from $68.1 million to $79.2 million, aligning with asset management principles to schedule projects appropriately. The Mersey Hydro Update is part of the non-confidential information discussed.
2026 ACE Plan Appendix E Page 6 of 17 Mersey Hydro Update Non-Confidential
AI summary The 2026 ACE Plan Appendix E discusses updates related to Mersey Hydro, focusing on non-confidential information. The document appears to address capital expenditure planning and renewable energy initiatives under Nova Scotia's regulatory framework.
2026 ACE Plan Appendix E Page 12 of 17 Mersey Hydro Update Non-Confidential
AI summary The text references an update on Mersey Hydro within the 2026 ACE Plan, specifically Appendix E, page 12, marked as non-confidential. The content appears to outline procedural or project-related information for regulatory review.
ties with drawing down 23 reservoirs. Consideration of impacts to communities and exposure of Mi’kmaw archaeological 24 resources are hard to quantify in a decommissioning (re-naturalized) scenario. Decommissioning 25 estimates are indicat...
AI summary The decommissioning of Mersey Hydro reservoirs presents complex challenges, including quantifying impacts on communities and Mi'kmaw archaeological resources, leading to unclassified estimates and higher contingency requirements due to these uncertainties.
2026 ACE Plan Appendix E Page 16 of 17 Mersey Hydro Update Non-Confidential
AI summary The text references the 2026 ACE Plan Appendix E, focusing on a Mersey Hydro Update. It indicates a non-confidential section of the plan discussing updates related to the Mersey Hydro project.
s more information is obtained, and the HIP is 23 continuously updated as forecasts are revised as result. 24 25 NS Power reiterates that it is committed to ensuring the Mi’kmaw, stakeholders, and the Board are 26 actively engaged prior to...
AI summary NS Power emphasizes stakeholder engagement for the Mersey Redevelopment project, relying on the 2025 Integrated Resource Plan (IRP) for decision-making. NPV figures exclude full system replacement costs, and a Capital Item (CI) application will be submitted post-IRP completion. Engagement with the Mi’kmaw and DFO is ongoing.
1 TABLE OF CONTENTS 2 3 1.0 EXECUTIVE SUMMARY ................................................................................................. 5 4 2.0 INTRODUCTION .............................................................................
AI summary The document outlines Nova Scotia's 2030 decarbonization goals, including 80% renewable electricity sales and coal phase-out, along with initiatives like the Clean Power Plan, Independent Energy System Operator, and Resource Development Plan focusing on wind, solar, and community programs.
.................................... 23 17 6.1.5 Commercial Net Metering ........................................................................ 25 18 6.1.6 Additional Renewable Energy Procurements ...........................................
AI summary The document outlines sections of an Integrated Resource Plan (IRP) action plan, including commercial net metering, battery storage projects, renewable energy integration, the NS-NB Reliability Intertie Project, fast-acting generation, fuel conversions, and coal phase-out initiatives. Key topics include renewable energy procurement, grid stability, and infrastructure planning.
ration Phase-Out................................................................................... 35 30 7.0 ADDITIONAL IRP ACTION PLAN AND ROAD MAP ITEMS ................................... 38 Page 2 of 55 Date: December 12, 2025 Page 65...
AI summary This document outlines the 2026 ACE Plan's update, covering demand-side management, hybrid peak/load management, green hydrogen projects, offshore wind, and project accountabilities, coordination, and risk management strategies for Nova Scotia's energy sector.
2026 ACE Plan Appendix F Page 4 of 55 The Path to 2030 – 2025 Update Non-Confidential 1 TABLE OF FIGURES 2 3 Figure 1 - 2030 Clean Power Plan Resources ................................................................................. 6 4 F...
AI summary The appendix lists figures related to Nova Scotia's 2030 Clean Power Plan, including project statuses for renewable energy initiatives, battery storage (Bridgewater BESS), and coal retirement timelines. It outlines the 2025 10-Year System Outlook Report and tracks progress on the Green Choice Program, PHP Wind, and Minas Highlands Wind projects.
for this year’s Path to 2030 update. With respect to 12 resources, sizing, and timing, this update to The Path to 2030 report is consistent with the 2025 13 10YSO report unless otherwise noted. 14 15 Figure 1 - 2030 Clean Power Plan Resour...
AI summary The document updates the 2030 Clean Power Plan resources, aligning with the 2025 10YSO report. It details renewable energy projects (wind, solar, storage) with their capacities and construction dates, including the NS Power BESS Project, Green Choice Program, and future procurement timelines.
Resources Stage 1 300 2027 20274 Stage 2 300 2029-2030 2029-20304 Page 6 of 55 Date: December 12, 2025 Page 659 of 782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan Appendix F Page 7 of 55 The Path to 2030 – 2025 Updat...
AI summary The document outlines energy resource plans including fuel conversions at existing units (e.g., Point Tupper 2, Lingan 1/3/4), new wind/solar capacity (1,139 MW), energy storage (200–400 MW), fast-acting generation (600 MW), and load management initiatives (150 MW) from 2025–2029. Projects are scheduled for 2027–2030 with specific capacity and commissioning dates.
600 Total Fuel Conversions 609 Load Management Initiatives 150 2025-2029 2025-2029 Total Coal Phase Out 1,229 1 1 Timing has been updated to reflect that this wind project will come online in phases. Please refer to Section 6.1.3.3 2 for f...
AI summary The document outlines Nova Scotia Power's strategy to integrate renewable and dispatchable resources through the Evergreen IRP Action Plan, emphasizing collaboration with stakeholders including the government, IPPs, EfficiencyOne, Mi’kmaw partners, and IESO-NS. It highlights flexibility in resource additions and coordination for The Path to 2030, incorporating load management and green hydrogen development.
ESO-NS. These parties will have 16 various accountabilities in the development and execution of projects that will add and integrate 17 both renewable and dispatchable resources to the grid. 18 Page 7 of 55 Date: December 12, 2025 Page 660...
AI summary The document references ESO-NS's role in integrating renewable and dispatchable resources into the grid, with a focus on the 2026 ACE Plan Appendix F. It outlines project development and execution responsibilities for stakeholders.
: 30 31 • The 2030 Decarbonization Goals 32 • The Province of Nova Scotia’s 2030 Clean Power Plan 33 • Creation of the Independent Energy System Operator of Nova Scotia (IESO-NS) Page 8 of 55 Date: December 12, 2025 Page 661 of 782 REDACTE...
AI summary The document outlines Nova Scotia's 2030 Clean Power Plan, the Integrated Resource Plan (IRP) Action Plan, and the creation of the Independent Energy System Operator of Nova Scotia (IESO-NS). It details resource development, project management, and timelines for meeting decarbonization goals.
2026 ACE Plan Appendix F Page 10 of 55 The Path to 2030 – 2025 Update Non-Confidential 1 3.0 2030 DECARBONIZATION GOALS 2 3 NS Power’s 2030 decarbonization goals are mandated under several legislative and regulatory 4 frameworks. Although...
AI summary NS Power must achieve 80% renewable electricity sales by 2030 under amended regulations, requiring an additional 1,100 GWh from independent producers and allowing out-of-province renewable sources. These goals are integrated into the Evergreen IRP and the 2030 Clean Power Plan.
urce outside Nova Scotia. 22 23 This requirement was incorporated into the most recent Evergreen IRP and is considered in the 24 2030 Clean Power Plan. 25 2 N.S. Reg. 110/2021. Page 10 of 55 Date: December 12, 2025 Page 663 of 782 REDACTED...
AI summary Nova Scotia's Environmental Goals and Climate Change Reduction Act mandates 80% renewable electricity by 2030 and coal phase-out by 2030. These targets are integrated into the Evergreen IRP and 2030 Clean Power Plan, with the 2026 ACE Plan Appendix F detailing implementation steps.
rovincial goal to phase out coal-fired electricity generation by 2030, the federal 2 13 Reduction of Carbon Dioxide Emissions from Coal-fired Generation of Electricity Regulations 4 14 prescribe various regulations on coal generating units...
AI summary Nova Scotia aims to phase out coal-fired electricity by 2030, aligning with federal regulations and the Evergreen Integrated Resource Plan (IRP). The Clean Electricity Regulations (CER), effective 2035, support Canada’s net-zero goal by 2050 and align with Nova Scotia Power’s strategy to use emitting generation in peaking capacity.
2026 ACE Plan Appendix F Page 12 of 55 The Path to 2030 – 2025 Update Non-Confidential 1 • Establishing an allowable emissions limit of 65 tonnes/GWh and the opportunity to 2 purchase additional offsets at 35 tonnes/GWh until the end of 20...
AI summary The 2026 ACE Plan Appendix F outlines emissions limits under the Clean Electricity Regulations (CER), including a 65 tonnes/GWh cap, offset purchase options at 35 tonnes/GWh until 2049, and pooling emissions for units commissioned by 2029. The CER also allows 'planned unit' exemptions for projects meeting specific milestones. Nova Scotia's 2030 Clean Power Plan is referenced as a framework for decarbonization.
ower Plan is 6 shown in Figure 2 below. 7 8 Figure 2 - Nova Scotia's 2030 Clean Power Plan (October 2023) 9 6 nova-scotia-clean-power-plan-presentation-en.pdf (novascotia.ca) Page 13 of 55 Date: December 12, 2025 Page 666 of 782 REDACTED R...
AI summary The document references Nova Scotia's 2030 Clean Power Plan and its 2025 update under the 2026 ACE Plan, highlighting the Path to 2030 initiative. It includes a figure and a link to a presentation, though key details are redacted.
2026 ACE Plan Appendix F Page 16 of 55 The Path to 2030 – 2025 Update Non-Confidential 1 6.0 RESOURCE DEVELOPMENT PLAN ELEMENTS 2 3 6.1 Wind and Solar Resources 4 5 The 2030 Clean Power Plan incorporates a significant quantity of new varia...
AI summary The 2030 Clean Power Plan includes the Rate Base Procurement (RBP) program, initiated by Nova Scotia in 2021 to secure 1,100 GWh of renewable energy. Four RBP projects totaling 306 MW are underway, with commercial operation dates ranging from late 2025 to 2026. NS Power collaborated with RBP Interconnection Customers on engineering and construction support in 2025.
1 projects to date: both IR-673 and IR-669 are expected to be in service in the near-term as per the 2 forecast COD table (Figure 3 above). In addition, both IR-668 and IR-677 are making progress in 3 engineering and construction to achiev...
AI summary The document discusses the progress of projects IR-673, IR-669, IR-668, and IR-677, and details the Green Choice Program (GCP), established under the 2022 Electricity Act amendments. The GCP aims to procure 1,500–2,000 GWh of low-impact renewable energy annually for large consumers, supporting Nova Scotia’s 2030 decarbonization goals. NS Power collaborates with the Department of Energy (DOE) and executes participant agreements for the program.
1 • Submitting an annual report, on or before January 31 of each year, to the Minister and the 2 Board as required under the Green Choice Program Regulations. 12 3 4 In January 2025, six renewable energy projects were selected by the Procu...
AI summary The Green Choice Program (GCP) selected six renewable energy projects in 2025, with two entering the System Impact Study phase. Projects like IR 732 – Eigg and IR 826 – Sugar Maple Wind have pending interconnection agreements and target COD in 2028. Nova Scotia Power (NS Power) will support development, while the Province announced a new procurement process in September 2025 to meet GCP capacity targets.
ades for each project. 17 18 In September 2025, the Province of Nova Scotia announced its intention to initiate a new 19 procurement process to ensure the GCP achieves its targeted capacity. 14 20 12 Green Choice Program Regulations - Elec...
AI summary The Province of Nova Scotia plans to restart a procurement process for the Green Choice Program (GCP) to meet its capacity targets after four projects withdrew. This follows regulatory updates and media coverage on wind energy procurement challenges, with context provided by the 2026 ACE Plan and related documents.
1 6.1.3 Prescribed Generation Facilities 2 3 In August 2024, the Province amended the Prescribed Energy-Storage Projects Regulations to 4 include prescribed generation facilities, creating the Prescribed Generation Facilities and Energy- 5...
AI summary Nova Scotia amended regulations in 2024 and 2025 to include prescribed generation facilities, capping total output at 1,140 MW. Seven wind projects, including three in The Path to 2030, are prescribed. The Port Hawkesbury Paper Wind project (168 MW) is under development, with construction progressing since 2024 and expected commercial operation by Q4 2026.
bases, pouring the foundation for the substation, and installing poles for the collection system.19 24 PHP Wind continues to forecast commercial operation to start in the fourth quarter of 2026. 25 15 Prescribed Generation Facilities and E...
AI summary PHP Wind's project progress includes site preparation and infrastructure development, with a forecasted commercial operation in Q4 2026. Regulatory references include the Prescribed Generation Facilities and Energy-Storage Projects Regulations and Bill 149, Powering the Offshore Act. The text also cites meeting minutes related to the project.
2026 ACE Plan Appendix F Page 20 of 55 The Path to 2030 – 2025 Update Non-Confidential 1 NS Power has been supporting the PHP Wind project as it moves through the GIP. There are 2 currently two IRs associated with the project. Goose Harbou...
AI summary NS Power is supporting the PHP Wind project through the Generator Interconnection Process (GIP), with two Information Requests (IRs) in progress. The Minas Highlands Wind Limited project (IR 762) is also advancing, with System Impact and Facilities Studies ongoing. Both projects aim for commercial operation by late 2026.
Agreement IR 762 – Minas In Progress In Progress Pending Dec 31, 2026 Highlands Wind 13 14 6.1.3.3 Renewable to Retail / Mersey River Wind Inc (IR 597 and IR 675) 15 16 The Renewable to Retail (RtR) electricity market was established in No...
AI summary The Renewable to Retail (RtR) electricity market in Nova Scotia, established in 2016, enables independent retailers to sell renewable energy directly to NS Power’s retail customers. The text references the Path to 2030 and the 2025 10 Year System Outlook, part of the 2026 ACE Plan Appendix F.
1 contain 148.5 MW of new wind generation proposed to supply RtR customers (IRs 597 and 675) 2 with first commercial operation anticipated in the fourth quarter of 2026. 3 4 On October 27, 2021, the Board approved an application by Renewal...
AI summary Renewall Energy Inc. seeks extensions to its deadline for selling renewable low-impact electricity under its Retail Supplier license. The Nova Scotia Energy Board (NSEB) has repeatedly approved extensions, with the latest deadline set to March 31, 2027. A conditional Power Purchase Agreement (PPA) was issued for the Mersey River Wind project, backed by the Minister of Energy.
on that the Canadian 22 Infrastructure Bank instructed Renewall to request a three-month extension as a contingency 23 against unforeseen schedule delays and so the request to extend the deadline for selling renewable 24 low-impact electri...
AI summary The Canadian Infrastructure Bank approved a three-month extension for Renewall to sell renewable low-impact electricity until March 31, 2027. Mersey River Wind Phase I is expected to reach commercial operation in Q4 2026, with NS Power supporting the project's transmission infrastructure. A Board Decision (M10293) from October 27, 2021, is referenced.
1 2 (IR 675) is forecast to reach commercial operation in Q1 2027, with the supporting operating 2 study to be completed beforehand to assess system impact. This will bring the total installed 3 capacity of the Mersey River Wind projects t...
AI summary The document outlines the progress of Mersey River Wind projects (Phases I and II) with capacities of 90 MW and 112.5 MW, respectively, and their expected commercial operation dates. It also notes the status of other interconnection requests (IR 739, IR 785) and the Generator Interconnection Process (GIP) for Renewable to Retail (RtR) projects.
- West Withdrawn Wind Farm 14 1 This is a change from the 2024 update as the EMT analysis for IR 597 was incorporated into the IR 675 15 plant model, which was modified to include both IR 597 and IR 675 as a single plant. 16 2 March 31, 20...
AI summary The 2026 ACE Plan incorporates EMT analysis for IR 597 into the IR 675 plant model, modifying it to combine both as a single plant. The first 54 MW of Mersey Wind 2 is scheduled for COD on March 31, 2027, reflecting updates to the 2024 IRP analysis.
1 6.1.4 Community Solar Program 2 3 The Community Solar Program launched in Q1 2024, following proclamation of amendments to 4 the Electricity Act 21 and the registration of the Community Solar Regulations. The program was 5 first conceive...
AI summary The Community Solar Program, launched in Q1 2024, aims to enable 50 MW of new community solar generation and equitable access to renewable energy. Administered by NS Power, it allows eligible entities (e.g., municipalities, First Nations, not-for-profits) to develop solar gardens with capacities between 0.5 MWac and 10 MWac. The first project, a 0.585 MW garden in Sydney, Cape Breton, enrolled 44 subscribers in March 2025.
1 • A 4.8 MW community solar garden in Brooklyn, Annapolis County 24 2 • A 1.7 MW community solar garden in Sydney 25 3 • A 2.2 MW community solar garden in West Petpeswick 26 4 5 The forecast commercial operation date for these three proj...
AI summary The text outlines three community solar projects in Nova Scotia with a combined capacity of 8.7 MW, slated for Q3 2027. NS Power has completed 31 preliminary assessments under the Community Solar Program, managed by the Provincial DOE. Projects require a PPA and DSIS studies. NS Power will file its first program report with the NSEB by January 31, 2027, per regulatory requirements and a Board Order.
1 6.1.5 Commercial Net Metering 2 3 April 2022 amendments to the Electricity Act (Nova Scotia) established the framework for a new 4 net metering program. October 2022 amendments to the Renewable Energy Regulations 29 required 5 that NS Po...
AI summary Nova Scotia Power Inc. (NS Power) implemented the Commercial Net Metering Program (CNMP) following 2022 legislative amendments. The program allows customers to generate renewable energy and export excess to NS Power, with energy credits applied annually. As of 2024, 4,140 kW of solar PV was installed, with 82% of requests for Class 1 service (up to 100 kW).
1 • The remaining 18 percent of requests were for Class 2 Commercial Net Metering Service 2 (Generators greater than 100 kW up to 1 MW). 3 • 12 percent of requests were for generators having a nameplate capacity greater than 200 4 kW (Name...
AI summary NS Power has completed 16 preliminary assessments under the Commercial Net Metering Program (CNMP), totaling 3.5 MW of potential capacity. Over 12.4 MW of capacity has been assessed since the program's start. Additional renewable energy procurement is needed beyond current projects to meet the 2030 80% renewable energy standard, with responsibility for future procurements falling to the government and IESO-NS.
ed a new procurement process should be initiated targeting 1,000 – 1,200 GWh of low- 26 impact renewable electricity in order to meet the 2030 80 percent renewable energy standard. 30 In 27 September 25, 2025, the Nova Scotia Energy Minist...
AI summary The document proposes initiating a procurement process targeting 1,000–1,200 GWh of low-impact renewable electricity to meet Nova Scotia's 2030 80% renewable energy standard. It references the Nova Scotia Energy Minister's announcement of reissuing a call for new renewable energy sources and seeking a new procurement administrator, citing M12386 and the 2025 10 Year System Outlook.
r new renewable energy sources and the Province was looking for a new procurement 2 administrator to lead this initiative. 31 3 4 6.2 Battery Storage & Renewable Integration Resources 5 6 The 2030 Clean Power Plan calls for deployments of...
AI summary The 2030 Clean Power Plan mandates grid-scale storage in Nova Scotia, with 150 MW of 4-hour storage approved in 2024. NS Power's BESS project (ECEI) includes updates on Bridgewater, Spider Lake, and White Rock Road sites, with commercial operations expected by late 2025 and mid-2026. The NSEB's decision (M11539) and interim report (M12494) are referenced.
final BESS site under this project, is on track for commercial operation in 24 July 2026. 25 31 Nova Scotia to redo wind energy procurement after 4 projects drop out CBC News Page 27 of 55 Date: December 12, 2025 Page 680 of 782 REDACTED R...
AI summary Nova Scotia amended the Electricity Act in 2023 to enable competitive procurement of energy storage via RFPs and contracts. The Province confirmed in 2024 that future energy storage capacity will be procured by IESO-NS through a competitive process, with timing and quantity determined by the IESO-NS.
1 capacity is required to maintain supply reliability while meeting growing peak demand 2 requirements and replacing firm capacity that will be retired to comply with the 2030 coal phase- 3 out policy requirements. NS Power’s further study...
AI summary NS Power requires 600 MW of fast-acting generation by 2030 to meet growing demand and replace retiring coal capacity, aligning with the 2030 coal phase-out policy and Clean Electricity Regulations (CER). Procurement responsibility shifted to IESO-NS in 2024, as outlined in The Path to 2030 – 2024 Update (M12012).
ls (fuel switching). 22 23 6.5 Fuel Conversions at Existing Units 24 25 The 2030 Clean Power Plan includes alternate fuel operation at four of NS Power’s existing 26 thermal units. Similarly, the Evergreen IRP identified that alternate fue...
AI summary The 2030 Clean Power Plan and Evergreen Integrated Resource Plan (IRP) propose alternate fuel operations at four NS Power thermal units. References include IESO-Nova-Scotia-REOI-for-Capacity.pdf and exhibits from M12412 related to expenditure and revenue requirements.
1 Extension Period). As such, E1’s prior five-year DSM Plan development was temporarily paused 2 while E1 prepared and filed its 2026 DSM Plan Extension Application, which remains an open 3 Matter before the Board. 43 E1’s 2026 DSM Plan ta...
AI summary E1's 2026 DSM Plan extension targets 528.7 GWh energy savings and 16.3 MW DR capacity with $236.8M investment. NS Power collaborates with DSMAG on cost-effectiveness frameworks and electrification strategies, focusing on affordability and peak load reduction through hybrid electrification scenarios.
1 developed with property owners and industry stakeholders, to explore new opportunities for 2 flexible load management in electrified multi-tenant settings. 3 4 Engagement efforts during the season included a kickoff meeting in November 2...
AI summary NS Power engaged stakeholders in 2024-2025 for flexible load management in multi-tenant settings, filed a TVP Season approach, and received Board approval to align tariffs with standard rates during system outages. The Board emphasized rate equity and program continuity, while NS Power concluded its SGNS project, validating DER coordination benefits for affordability and reliability.
n orchestrating diverse DER assets to provide 25 measurable system benefits. Following the Board’s October 2024 decision on the SGNS Final 26 Report (M11621), NS Power initiated the Distributed Energy Resource Integration Roadmap 27 (DERIR...
AI summary NS Power initiated the Distributed Energy Resource Integration Roadmap (DERIR) following the Board’s October 2024 decision on the SGNS Final Report, engaging Dunsky Energy + Climate Advisors for jurisdictional scans, framework development, and stakeholder engagement.
1 2 Through 2025, NS Power has made steady progress on the DERIR initiative. The initial 3 framework, first stakeholder workshop, development of list of DER-related initiatives, second 4 stakeholder workshop, and one-on-one interviews with...
AI summary NS Power has advanced the DERIR initiative through stakeholder engagement and planning, while exploring green hydrogen projects with developers like EverWind Fuels and Nova Sustainable Fuels. These projects require incremental resources beyond current load forecasts, highlighting the need for additional capacity and renewable energy integration.
and the significant load requirement, the following outlines 25 the common approach by the developers: 26 27 • Developers will self-develop and supply renewable resources including a mix of wind, 28 solar and battery storage (depending on...
AI summary Developers plan to self-develop renewable resources (wind, solar, battery storage) and require a new tariff structure for grid interaction. This is outlined in the 2026 ACE Plan Appendix F, highlighting grid integration challenges and renewable energy deployment strategies.
2026 ACE Plan Appendix F Page 44 of 55 The Path to 2030 – 2025 Update Non-Confidential 1 o Top up in hours when their self-supplied resources do not meet their firm load 2 requirements or, in some cases, when additional resources are requi...
AI summary The 2026 ACE Plan Appendix F discusses hydrogen development and offshore wind initiatives in Nova Scotia. It references the Province’s Green Hydrogen Action Plan (2023) and outlines offshore wind procurement goals (5 GW by 2033–2035). NS Power’s IRP Roadmap Item 11 assesses hydrogen tariff impacts on the Action Plan.
en industry. Since that time, the NS 23 DOE has established an offshore wind procurement schedule, which would see the initiation of 24 offshore wind operations in approximately 2033 – 2035. 25 48 https://novascotia.ca/green-hydrogen/docs/...
AI summary The Nova Scotia Department of Energy (NS DOE) has established an offshore wind procurement schedule, with operations expected to begin between 2033 and 2035. This initiative aligns with broader renewable energy goals outlined in the 2026 ACE Plan.
1 The following are existing and future milestones to enable this: 2 3 • NRCan and the NS DOE designated Wind Energy Areas (WEA), which will be managed 4 by the Canada Nova Scotia Offshore Energy Regulator (CNSOER), in July 2025. 5 6 • A s...
AI summary Nova Scotia's offshore wind development includes milestones like WEA designation in 2025, strategic direction letters, and a 2026 bid process. While not part of the 2030 Clean Power Plan, NS Power monitors progress. The NZA-led study (2024-2026) evaluates offshore wind's potential for decarbonization, hydrogen, and export opportunities, with transmission planning phases ongoing.
ission expansion plan to support OSW, respectively. Ultimately, this study is 26 anticipated to be completed in Q1 2026 and will provide a thorough understanding of the 27 opportunities and challenges for integrating OSW into the Atlantic...
AI summary The document discusses a study on integrating offshore wind (OSW) into the Atlantic Canadian grid, led by NZA with NS Power's participation. The study, anticipated to complete in Q1 2026, will assess opportunities and challenges for provincial and regional integration, including domestic and export considerations.
1 8.0 PROJECT ACCOUNTABILITIES, COORDINATION, AND RISK 2 MANAGEMENT 3 4 NS Power believes that the Nova Scotia 2030 Clean Power Plan is a comprehensive and 5 appropriate clean energy transition plan. It is based on extensive studies and st...
AI summary NS Power asserts the Nova Scotia 2030 Clean Power Plan is comprehensive, based on stakeholder engagement and studies. It outlines roles: Province manages renewable projects until 2030 RES targets, NS Power handles fuel conversions and transmission, and IESO-NS oversees battery storage and fast-acting generation.
• Transition • Take • Coordinate • IPPs develop Stability responsibility to responsibility for preferred IPP renewable projects and Renew- identify required identifying project siting in compliance able assets through IPP required assets b...
AI summary The document outlines a framework for integrating renewable energy projects through Independent Power Producers (IPPs), emphasizing system studies, compliance with NS Power’s transmission requirements, and procurement via a utility-regulated model. It references the 2026 ACE Plan Appendix F and a 2025 update to 'The Path to 2030.'
competitive procurements for required products and services. 1 2 8.2 Implementation Coordination 3 4 The Province of Nova Scotia and NS Power are both committed to meeting 2030 coal phase-out 5 and 80 Percent Renewable Energy Standard targ...
AI summary Nova Scotia and NS Power collaborate on 2030 coal phase-out and 80% renewable energy targets through a Working Group, emphasizing program coordination and risk management for capital-intensive initiatives. The 2026 ACE Plan Appendix F outlines implementation strategies and risk mitigation frameworks.
1 project delays. Talent shortages have the potential to affect NS Power, its partners 2 across the province, and its contractors and suppliers. 3 4 4. Project Approvals 5 • 2025 Trend: No Change 6 • The 2030 Clean Power Plan requires the...
AI summary The text highlights project delays due to talent shortages impacting NS Power and partners, the need for approvals under the 2030 Clean Power Plan, risks in transitioning to fast-acting generation by 2027-28, and the publication of the Clean Electricity Regulations (CER) aligning with Nova Scotia policy. Key issues include environmental and regulatory approvals, procurement challenges, and renewable energy targets.
6. Evolving Policy Landscape 26 • 2025 Trend: Reduced Risk 27 • The final CER was published on December 18, 2024 and is in alignment with NS 28 Power’s current long-term strategy as it supports the use of emitting generation in 29 a peakin...
AI summary The 2025 update outlines alignment of the Clean Electricity Regulations (CER) with NS Power's strategy, emphasizing peaking generation and electrification policy impacts. Policy changes through 2030 will involve NERC, NPCC, and provincial/federal electrification policies. NS Power will adapt via its IRP Roadmap.
1 9.0 CONCLUSION 2 3 The Nova Scotia 2030 Clean Power Plan and The Path to 2030 represent a comprehensive clean 4 energy transition plan that is aligned with NS Power’s most recent IRP Action and Roadmap 5 update. Delivering on this plan w...
AI summary The Nova Scotia 2030 Clean Power Plan and The Path to 2030 outline a clean energy transition aligned with NS Power’s Integrated Resource Plan (IRP). Key 2025 progress includes wind farm construction, Power Purchase Agreements (PPAs) for 262 MW of wind capacity, Battery Energy Storage System (BESS) developments, NSEB approval for the Reliability Intertie project, and community solar initiatives.
1 Nevertheless, there are growing risks with some aspects of the plan, including: 2 3 • Delays in procuring new fast-acting generation, combined with the growing lead times seen 4 across the industry for new combustion turbines, create unc...
AI summary The text outlines risks in a plan, including delays in procuring fast-acting generation, attrition of Green Choice projects risking 80% renewable energy targets, and unclear timelines for energy storage beyond NS Power’s BESS project. NS Power notes flexibility in coal retirement timelines but emphasizes collaboration with IESO-NS and the Province to address procurement challenges.
................................ 62 17 7.3.1 Connected Assets ...................................................................................... 62 18 7.3.2 Fault Location Isolation and Service Restoration ................................
AI summary The document outlines sections of a reliability plan update by NS Power, focusing on connected assets, fault location isolation, and distributed energy resources (DERs). Appendices detail priority feeders and pole monitoring projects, while the 2026 ACE Plan Appendix G is referenced as part of the non-confidential update.
2026 ACE Plan Appendix G Page 43 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 6.0 ADVANCED GRID MODERNIZATION PROGRAMS 2 3 2025-2029 Forecast Investment: $78 million 4 Forecasted Performance Standards SAIDI Reducti...
AI summary NS Power's Advanced Grid Modernization Program (2025-2029) aims to enhance grid reliability and efficiency through three initiatives: Connected Assets (real-time device control), FLISR (automated outage response), and DER integration. The $78 million investment targets a 0.06-0.11 SAIDI reduction.
n 104H In Design. Metro Kempt Rd (multiple devices) Planned for 2026 Execution 1 2 6.2 Fault Location Isolation and Service Restoration 3 4 2025-2029 Forecast Investment: $13 million 5 2025 Anticipated Year End Investment: $1.6 million 6 7...
AI summary NS Power advanced FLISR initiatives in 2025 through planning and standardization efforts, with a $13 million investment forecast for 2025-2029. The text also discusses the growing impact of DERs on electricity generation and consumption dynamics as the country transitions to net-zero.
aditional centralized dispatch as evidenced by growing numbers of net-metered connections. This 24 shift introduces new complexities for power utilities, particularly with respect to maintaining Page 47 of 71 Date: December 12, 2025 Page 7...
AI summary The document discusses NS Power's Five-Year Reliability Plan update, highlighting challenges from increasing net-metered connections and their impact on centralized dispatch and grid reliability. It emphasizes complexities for power utilities in maintaining system reliability amid distributed energy resource growth.
2026 ACE Plan Appendix G Page 48 of 71 NS Power Five-Year Reliability Plan - Update Non-Confidential 1 reliability and operational flexibility. To address these challenges, enhanced visibility, automation, 2 and control of DERs is importan...
AI summary NS Power's 2026 ACE Plan Appendix G discusses the integration of distributed energy resources (DERs) to enhance grid reliability and decarbonization. It highlights the DERMS project, stakeholder engagement, and alignment with Nova Scotia's 2030 Clean Power Plan, emphasizing coordinated DER management for system resilience.
with the province’s 2030 17 Clean Power Plan, and is intended to ensure DERs are deployed in a manner that enhances system 18 reliability, supports decarbonization, and delivers customer value. Page 48 of 71 Date: December 12, 2025 Page 75...
AI summary The text references the province’s 2030 Clean Power Plan, emphasizing the deployment of DERs to enhance system reliability, support decarbonization, and deliver customer value. It also mentions an update to NS Power’s Five-Year Reliability Plan and Appendix G of the 2026 ACE Plan.
ion 104H In Design. Metro Kempt Rd (multiple devices) Planned for 2026 Execution 2 3 7.3.3 Distributed Energy Resources (DERs) 4 5 As the presence of Distributed Energy Resources (DERs) such as solar, wind, and battery storage 6 continues...
AI summary The document discusses the importance of managing Distributed Energy Resources (DERs) such as solar, wind, and battery storage to maintain grid reliability and efficiency. NS Power plans to implement a DERMS platform through a capital work order in 2026 to enhance grid resilience and intelligence.