99785Board Letter re: Accepted as filed 1 passage
M12494 – Nova Scotia Power Inc. – Battery Energy Storage System Project – Interim Report p. pp. 0-1
M12494 – Nova Scotia Power Inc. – Battery Energy Storage System Project – Interim Report On June 13, 2024, the Nova Scotia Utility and Review Board (NSUARB) approved Nova Scotia Power Inc.'s (NS Power) application for its Capital Investmen...

AI summary Nova Scotia Power Inc. received approval for its $237.7 million Battery Energy Storage System (BESS) Project, which includes three sites with a combined capacity of 150 MW. The project is progressing on schedule, with two sites expected to operate in November 2025 and the third in July 2026. As of August 2025, costs are in line with initial estimates and contingency funds have not been used.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →