S-1Notice of Appeal (redacted) 1 passage
12 Mar email to the... p. p. 5
12 Mar email to the... Once an actual meter reading is obtained following estimated meter readings, all estimation error is reconciled. Final Written DRO Decision: In the context of Board approved Regulation 5.1, N.S.Power has appropriatel...

AI summary The DRO confirms that N.S. Power appropriately billed the customer after reconciling estimated meter readings with actual readings under Regulation 5.1. The decision can be appealed to the Nova Scotia Energy Board (NSEB), with contact details provided.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →