On March 31, 2025, the NSPSO submitted its first Annual Interconnection Process Proceeding Report (M12174) to the NSEB. The report provided a summary of its compliance status regarding Synapse's recommendations and the additional Board dir...
AI summary The NSPSO submitted an Annual Interconnection Process Proceeding Report (M12174) to the NSEB, addressing compliance with Synapse's recommendations and Board directives from M10905. The Board combined M10905 and M12174 for concurrent consideration, directed a stakeholder conference after public comments, and received feedback from Synapse, SBA, Natural Forces, and ESC. NS Power responded to comments, and the NSEB issued a decision in M10905/M12174.
In its letter of December 23, 2025, the Board provided the following with respect to further consideration of matter M12524: The panel intends to seek comments about Concentric's report and recommendations from participants in Matters M109...
AI summary The Nova Scotia Energy Board (NSEB) is seeking input on Concentric's report and recommendations related to FERC Order 2023. The IESO-NS confirmed responsibility for addressing the report and has submitted a letter outlining its plans for the annual interconnection processes report. The NSPSO will handle distribution-related reporting, while IESO-NS handles transmission-related reporting.
DATE FILED: March 31, 2026 Page 12 of 33 1 2 workshops.10 the completion of the 3 NS Power scheduled two workshops, one in April 2025 and another in May 2025. The Company 4 held the first session April 17, 2025, as planned, and invited sta...
AI summary NS Power conducted two stakeholder workshops in 2025, but canceled the second due to lack of feedback. The NSEB accepted the compliance report. A cybersecurity incident impacted the distribution hosting capacity map, which remains temporarily unavailable. The Board directed NS Power to consider the connect and manage approach beyond current ERIS practices after reviewing FERC Order 2023.