Appellant conditionally agrees to meter test in NSPI billing dispute, rejecting smart meter replacement; NS Power confirms it will proceed with digital meter swap and testing
AI summary
- Appellant Jillian Atwell Coxhead agreed to a meter test only on the condition that her analog meter be replaced with a digital meter rather than a Advanced Metering Infrastructure smart meter, citing concerns about fire risk and inaccurate readings from smart meters (Exhibit 102439).
- Ms. Coxhead reported receiving a $5,000 power bill and alleged a $860 charge during a 65-day period in which she states she shut off her main panel and ran a generator, calling into question the accuracy of her current metering and Billing Procedures (Exhibit 102439).
- NS Power's Regulatory Counsel Kathleen Murray confirmed that the utility will proceed with removing the existing meter, replacing it with a digital meter, and conducting a formal meter test, with results and supporting documentation to be provided to the Board and Ms. Coxhead (Exhibit 102445).
Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →
What was filed
Documents filed on this day
- 102439 Appellants Response re Having Meter Tested (redacted)
- 102445 NSPI Response re Having Appellants Meter Tested (redacted)