B-3 Exhibits 06/18/2026

TOB (NSEB) RIR 1 to 42 - Redacted

Download original
B-3.pdf · PDF · 3.5 MB · 55 pages
AI overviewWhat this document contains

This document is an exhibit (Exhibit B-3) from a regulatory intervenor response (RIR) filed with the Nova Scotia Energy Board. It contains a series of interrogatory responses addressing technical specifications, project costs, maintenance plans, equipment lifespans, O&M costs, hydrology data, and other aspects of a hydroelectric refurbishment project at the Factorydale facility.

Disclaimer: This overview was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →

Filed in: M12795 — Town of Berwick Electric Commission - Factorydale Hydropower Plant Refurbishment - $6,000,000

Filing event: RIR on 06/18/2026 · View digest →

55 pages
100%