Home›Entities›Nrcan
Entity — organization

NRCan

54 matters involved in 132 documents 10 topics engaged with
By this entity
Filter & sort

54 matters on the record

Matters involved in

M131422026
NSP Maritime Link Inc. (NSPML) - 2026 Q3 Quarterly Report Open
→
M130832026
Nova Scotia Power Inc. - CI C0068718 – IT - DERMS Solution Project - $2,965,414 Open
→
M130502026
Town of Mahone Bay Electric Utility - Edgewater Project $2,650,000 Open
→
M130422026
Procurement Administrator - Power Advisory - Application for Approval of the Green Choice Power Purchase Agreement Open
→
M130142026
Nova Scotia Power Inc. - CI C0068719 - IT - Distributed Intelligence Apps - $3,165,790 Closed
→
M129362026
NSPI DRO Appeal - Billing Issues - Paul Douglas Meade Open
→
M129322026
Nova Scotia Power Inc. (NSPI) - Time-Varying Pricing Pilot Program - 2024/25 (Year Four) and 2025/26 (Year Five) Evaluation Reports Open
→
M128612026
Nova Scotia Power Inc. (NSPI) - 2026 Load Forecast Report Closed
→
M128352026
Nova Scotia Power Inc. - Annual and Regulated Financial Statements - 2025 Open
→
M128222026
EfficiencyOne - 2025 Audited Financial Statements - December 31, 2025 Closed
→
M127952026
Town of Berwick Electric Commission - Factorydale Hydropower Plant Refurbishment - $6,000,000 Closed
→
M127802026
EfficiencyOne - 2027-2031 Demand Side Management (DSM) Plan Application Open
→
M126652026
Nova Scotia Power Inc. - Fuel Adjustment Mechanism (FAM) Audit, conducted by Bates White for 2024 and 2025 Open
→
M126632025
Nova Scotia Independent Energy System Operator (IESO Nova Scotia) - 2026/2027 Revenue Requirement and Fees Application Open
→
M126192025
Nova Scotia Power Inc. - 2026 Annual Capital Expenditure (ACE) Plan - $284 million Closed
→
M125932025
Nova Scotia Power Inc. - CI C0053696 – ECC Wind Integration - $4,428,335 Closed
→
M125922025
Nova Scotia Power Inc. - CI 47751 – ECC Dynamic Line Rating Implementation - $2,148,364 Closed
→
M125912025
Nova Scotia Power Inc. - CI C0032664 – Energy Control Centre – Optimization Tools - $7,486,068 Closed
→
M125582025
Review of NS Power's Five-Year Reliability Plan 2025-2029 Open
→
M124942025
Nova Scotia Power Inc. - Battery Energy Storage System Project (BESS) – Interim Report Closed
→
M124512025
Nova Scotia Power Inc. - 2026 General Rate Application (GRA) Closed
→
M124172025
Nova Scotia Power Inc. - CI C0071528 – FLISR Implementation – $4,638,245 Closed
→
M123492025
Nova Scotia Power Inc. (NSPI) - 2025 Load Forecast Report Closed
→
M122822025
EfficiencyOne - New Benefit Cost Analysis Test for Evaluating Demand Side Management (DSM) Plans Closed
→
M122492025
EfficiencyOne - 2026 DSM Extension Application Closed
→
M122412025
EfficiencyOne - 2024 Audited Financial Statements - December 31, 2024 Closed
→
M121862025
EfficiencyOne - 2024 DSM Annual Progress Report and 2024 DSM Evaluation Reports Closed
→
M121772025
Nova Scotia Power Inc. - Distributed Energy Resource (DER) Integration Roadmap Open
→
M119832024
EfficiencyOne 2024 Q3 Demand Side Management (DSM) Report Closed
→
M119272024
Nova Scotia Power Inc. - CI 50518 – HYD Ruth Falls Main Dam Refurbishment – $15,445,508 (ATO) Closed
→
M116892024
Nova Scotia Power Inc. (NSPI) - 2024 Load Forecast Report Closed
→
M116772024
EfficiencyOne - 2023 Audited Financial Statements - December 31, 2023 Closed
→
M116302024
EfficiencyOne - 2023 DSM Annual Progress Report and 2023 DSM Evaluation Reports Closed
→
M113072023
P-884 - Nova Scotia Power Inc. - 2023 Evergreen Integrated Resource Plan (IRP) - Action Plan and Roadmap Closed
→
M111082023
P-194 - Nova Scotia Power Inc. (NSPI) - 2023 Load Forecast Report Closed
→
M110942023
E-ENS-F-23 - EfficiencyOne - 2022 Audited Financial Statements - December 31, 2022 Closed
→
M105692022
P-194 - Nova Scotia Power Inc. (NSPI) - 2022 Load Forecast Report Closed
→
M105632022
E-ENS-F-22 - EfficiencyOne - 2021 Audited Financial Statements - December 31, 2021 Closed
→
M104732022
E-ENS-R-22 EfficiencyOne 2023-2025 Demand Side Management (DSM) Plan Application Closed
→
M096892020
E-ENS-F-20 - EfficiencyOne - 2019 Audited Financial Statements - December 31, 2019 Closed
→
M091632019
E-ENS-F-19 - EfficiencyOne - 2018 Audited Financial Statements - December 31, 2018 Closed
→
M090962019
Approval of a Supply Agreement for Electricity Efficiency and Conservation Activities between EfficiencyOne (E1) and Nova Scotia Power Inc.(NS Power), the establishment of a final agreement between the parties, and approval of a 2020-2022 Demand Side Management (DSM) Resource Plan Closed
→
M089292018
P-884 - Nova Scotia Power Inc. (NSPI) - Integrated Resource Planning (IRP) and M08059--Generation Utilization and Optimization Closed
→
M086042018
E-ENS-R-18 - EfficiencyOne - 2019 Demand Side Management (DSM) Plan Application, 2017 Annual Progress Report and 2017 Evaluation Reports Closed
→
M075442016
E-ENS-R-16 - EfficiencyOne - Incentive Setting Methodology Review and Recommendations Closed
→
M067332015
E-ENS-R-15 - EfficiencyOne Application for approval of a Supply Agreement for Electricity Efficiency and Conservation Activities between Efficiency One and Nova Scotia Power Inc.- NSPI - 2016-2019 DSM Plan Closed
→
M048192012
E-ENSC-R-12 - Efficiency Nova Scotia Corporation - Application for Approval of its Demand Side Management (DSM) Plan for 2013 - 2015 Closed
→
M036692010
E-ENSC-R-10 - Efficiency Nova Scotia Corporation - Electricity Demand Side Management Plan for 2012 Closed
→
M036662010
P-188 - NSPI Regulation 3.6 - Net Metering - Request approval of the revised Regulation 3.6 Closed
→
M036322010
BRD-E-R-10 - Renewable Energy Community Feed-in Tariffs (COMFIT) Closed
→
M035892010
CI# 40103 - P-510 - NSPI WO - Load Control Demonstration Project (U&U) - $4,293,793 Closed
→
M034522010
ENSC-TRAN - Efficiency Nova Scotia - Nova Scotia Power Inc. - Demand Side Management Transition Plan Closed
→
M034132010
CI# 39323; CI# 39626; CI# 39627; & CI# 39628 - P-128.10 - NSPI WO - (Digby Wind Project) Application for approval of capital work orders in the amount of $82.8 million for the acquisition, construction and interconnection of the Digby Wind Farm Project Closed
→
M042651999
P-871 - Nova Scotia Power Inc. - Application for a Load Retention Rate (2000) Closed
→