CI# 28726 - P-128.10 - NSPI WO - HYD - Carlton Lake Dam Refurbishment - $3,104,448
What's happened
Filing Timeline
-
DocumentNova Scotia Power filed a capital work order application seeking UARB approval for $3,104,448 to refurbish the Carlton Lake Dam on the Tusket Hydro System to meet Canadian Dam Association safety guidelines and DFO fish passage requirements.
The filings themselves
Documents
Exhibits
1 file
- N-1 Redacted Work Order 4/30/2010
What's discussed — click to drill in
Topics
Capital Expenditures
15 passages across 1 documents
Infrastructure Planning
12 passages across 1 documents
Rates And Money
3 passages across 1 documents
Contract Terms
2 passages across 1 documents
Cost Considerations
2 passages across 1 documents
Generation Grid Resources
2 passages across 1 documents
Regulatory Approval Processes
2 passages across 1 documents
Affordable Multifamily Housing And Non Profit Organizations Amf
1 passages across 1 documents
Cost To Customer
1 passages across 1 documents
Environmental Compliance
1 passages across 1 documents
Harmonized Sales Tax
1 passages across 1 documents
Regulatory Compliance
1 passages across 1 documents
Regulatory Oversight
1 passages across 1 documents
System Reliability
1 passages across 1 documents