CI C0061003 – POA LP HP IP Turbine Refurbishment (NSEB M12370) NSPI Responses to NSEB Information Requests 1 Request IR-11: 2 3 Regarding the Project Cost Estimate Input Checklist and Maturity Matrix on pages 4 to 5 4 of the application: 5...
AI summary NSPI responds to NSEB's information request regarding the turbine refurbishment project, explaining that the project cost estimate is classified as Class 3 due to risk and uncertainty factors, despite 97% of Class 1 deliverables being complete. It also notes that the checklist excludes power generating facilities and high voltage transmission as per AACE International standards.