M12370 Closed Electricity

Nova Scotia Power Inc. - CI C0061003 – POA LP HP IP Turbine Refurbishment – $4,861,261

Filed 07/07/2025 9 documents

What's happened

Filing Timeline

  • 20 Aug
    Decision
  • 11 Aug
    RIR
  • 18 Jul
    Document
  • 07 Jul
    Document

The filings themselves

Documents

Key documents 1 file
  • 99030 Board Decision Letter PDF · 08/20/2025
Exhibits 4 files
  • N-1 Application - Redacted PDF · 07/07/2025
  • N-1(C) Application - Confidential PDF · 07/07/2025
  • N-2 NSPI (NSEB) RIRs 1-14 - Redacted PDF · 08/11/2025
  • N-2(C) NSPI (NSEB) RIRs 1-14 - Confidential PDF · 08/11/2025
Other documents 4 files
  • 98422 Letter NSPI re: Capital Items Filed Outside the Quarter Package PDF · 07/07/2025
  • 98595 NSEB (NSPI) IR-1 to IR-14 PDF · 07/18/2025
  • 98916 Letter enclosing IR responses PDF · 08/11/2025
  • 99030 Board Decision Letter PDF · 08/20/2025

What's discussed — click to drill in

Topics

Capital Expenditures
18 passages across 6 documents
Asset Management
9 passages across 3 documents
Renewable Energy
7 passages across 3 documents
Infrastructure Planning
6 passages across 3 documents
Regulatory Approval Processes
6 passages across 4 documents
System Reliability
5 passages across 4 documents
Cost Considerations
4 passages across 3 documents
Rate Design
4 passages across 4 documents
Confidentiality
3 passages across 3 documents
Energy Efficiency Resource Assessment Model
3 passages across 2 documents
Integrated Resource Plan
3 passages across 3 documents
Planned Outage
3 passages across 2 documents
Rate Base
3 passages across 3 documents
2025 Ace Plan
2 passages across 2 documents
Capacity Costs
2 passages across 1 documents
Capacity Market Participation
2 passages across 2 documents
Generation Grid Resources
2 passages across 1 documents
Procurement Practices
2 passages across 2 documents
Rates And Money
2 passages across 2 documents
Accounting Standards
1 passages across 1 documents
Carbon Capture Utilization And Storage
1 passages across 1 documents
Cost Deferral
1 passages across 1 documents
Cost Effectiveness
1 passages across 1 documents
Cost Recovery
1 passages across 1 documents
Distribution Planning
1 passages across 1 documents
Electricity Efficiency And Conservation Act Nova Scotia
1 passages across 1 documents
Energy Efficiency Budgets
1 passages across 1 documents
Fuel Cost Adjustment
1 passages across 1 documents
Power Purchase Agreement
1 passages across 1 documents
Project Schedule
1 passages across 1 documents
Public Utilities Act Nova Scotia
1 passages across 1 documents
Regulatory Oversight
1 passages across 1 documents
Renewable Electricity Regulations
1 passages across 1 documents
Resource Costs
1 passages across 1 documents
Revenue Requirement
1 passages across 1 documents