NSPI - Request for final cost approval for CI# 35882 - 2009 Cutout Replacements - P-509 The Board has reviewed Nova Scotia Power Inc.'s ("NSPI") letter dated September 2, 2010 requesting Board approval for the following final cost work ord...
AI summary Nova Scotia Power Inc. (NSPI) requested approval for a $132,458 increase in the final cost of CI#35882 (2009 Cutout Replacements), citing higher direct labor, overheads, extended construction interest costs, and reduced contracted costs. The Board originally approved the project in 2009 for $1,510,053 and now confirms approval for the increased amount of $1,642,511.