Topic/Matter Intersection

Topic:"Generation Grid Resources" in M12962

Matter: Nova Scotia Power Inc. - CI C0068659 – TRE5 – IP-LP Turbine Refurbishment - $2,963,160 (ATO)
1 passage 1 document

Generation Grid Resources across all matters →

103350NSEB (NSPI) IR-1 to IR-9 1 passage
Request IR-4:
Request IR-4: - a) What is the current rated capacity in MW of Trenton Unit 5? - b) Please compare Trenton Unit 5's annual energy production data to NS Power's total annual generation for each year since the last maintenance outage in 2012...

AI summary Request IR-4 includes four questions regarding Trenton Unit 5, focusing on its rated capacity, energy production compared to NS Power's total generation, and its classification in terms of emissions and cost relative to other thermal generating units.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →