HomeRenewable EnergyM12372Evidence
Topic/Matter Intersection

Topic:"Renewable Energy" in M12372

Matter: Nova Scotia Power Inc. - CI C0067906 – POA Boiler Refurbishment 2025 – $1,218,254
2 passages 2 documents

Renewable Energy across all matters →

N-2NSPI (NSEB) RIR 1 to 5 1 passage
Date Filed: August 22, 2025 NSPI (NSEB) IR-4 Page 1 of 1 p. p. 13
Date Filed: August 22, 2025 NSPI (NSEB) IR-4 Page 1 of 1 1 Request IR-5: 2 3 Reference to 2025 10-Year System Outlook (M12386), page 17 of 64 (Figure 7), NS Power 4 notes that Point Aconi will be retired on 2029/2030. 5 6 (a) How does the...

AI summary The document outlines a request for information regarding NS Power's boiler refurbishment at Point Aconi Generating Station and its alignment with the 80% renewable energy generation goal by 2030. NS Power responds that the refurbishment ensures safe and reliable operation through the station's planned retirement in 2029/2030, supporting system reliability during the energy transition.

98779NSEB (NSPI) IR 1 to 5 1 passage
Request IR-5:
Request IR-5: - Reference to 2025 10-Year System Outlook (M12386), page 17 of 64 (Figure 7), NS Power notes that Point Aconi will be retired on 2029/2030. - a) How does the proposed boiler refurbishment align with NS Power's goal of achiev...

AI summary Request IR-5 seeks clarification on NS Power's boiler refurbishment plans, maintenance strategies for the Point Aconi Generating Station, and whether these will be adjusted in light of its planned retirement by 2029/2030, in alignment with NS Power's 2030 renewable energy goal.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →