Contingency Report #2 - Redacted
101837.pdf · PDF · 1.5 MB · 6 pages
AI overviewWhat this document contains
This document is an exhibit filed as part of an application batch in a Nova Scotia Energy Board regulatory matter. It contains a contingency report related to the Ruth Falls Main Dam Refurbishment project, outlining approved amounts, actual spending, and unbudgeted expenditures, including additional costs for water supply arrangements, meals, Mi'kmaq engagement, and administrative overheads.
Disclaimer: This overview was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →
Filed in: M11927 — Nova Scotia Power Inc. - CI 50518 – HYD Ruth Falls Main Dam Refurbishment – $15,445,508 (ATO)
Filing event: APPLICATION on 05/01/2026