Reply Submission - NSPI
101919.pdf · PDF · 204.1 KB · 6 pages
AI overviewWhat this document contains
This document is a reply submission filed by Nova Scotia Power Inc. (NS Power) in a Nova Scotia Energy Board (NSEB) regulatory matter. It covers NS Power's response to feedback on the RTU Replacement Program – Phase 6, including discussions on labour hour estimates, cost reasonableness, reporting requirements, and the impact of a 2025 cyber incident on data availability.
Disclaimer: This overview was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →
Filed in: M12550 — To obtain a cost reasonableness review of NS Power - CI C0051815 – $5,959,515 - RTU Replacements Program – Phase 6, as outlined in Section 2.1 of the ACE 2025 decision (M12012)
Filing event: APPLICATION on 05/08/2026