CI# 39844 - P-510 - NSPI WO - U&U Removal of Frost Casing on Gulch Surge Tank $545,604
What's happened
Filing Timeline
-
OrderNSUARB approved Nova Scotia Power's $454,604 unforeseen and unbudgeted work order for removal of deteriorated frost casing on the Gulch Surge Tank at the Bear River Hydro System.
The filings themselves
Documents
Key documents
1 file
- 05028 Board Decision Letter 8/19/2010
Exhibits
1 file
- N-1 Non-Confidential Work Order 7/30/2010
Other documents
1 file
- 05028 Board Decision Letter 8/19/2010
What's discussed — click to drill in
Topics
Capital Expenditures
5 passages across 2 documents
Regulatory Approval Processes
2 passages across 2 documents
Asset Management
1 passages across 1 documents
Budgets And Targets
1 passages across 1 documents
Capacity Costs
1 passages across 1 documents
Harmonized Sales Tax
1 passages across 1 documents
Infrastructure Planning
1 passages across 1 documents
Procurement Practices
1 passages across 1 documents
System Reliability
1 passages across 1 documents