N-1Non-Confidential Work Order 7/30/2010
4 passages
CI 39844 U&U Removal of Frost Casing on Gulch Surge Tank REDACTED July 30, 2010 An Emera Company UARB APPRO VAL SHEET Project Title: Removal of Frost C Casing on Gulch Su rge Tank U&U CI Number: 39844 Capital Project Authorization · . Head...
AI summary The document outlines a capital project for the removal of frost casing on the Gulch Surge Tank by an Emera Company. The project has an estimated cost of $454,604, with an estimated start date in August 2010 and an in-service date in October 2010. The submission was made on behalf of Nova Scotia Power Incorporated and approved by the Nova Scotia Utility and Review Board.
~rent CI Number Cost Centre 410 • 410·Bear River Hydro System Budget Version 2010 06/06 Forecast Start 08/15/2010 Operational 10/01/2010 Forecast Final Cost 10/30/2010 2010 $454,604.46 Total: $454,604.46 Original Cost: $0.00 The scope of w...
AI summary The document outlines a budget for the Bear River Hydro System in 2010, detailing the removal of deteriorated frost casing on a surge tank and the installation of a bubbler to prevent freezing. The scope of work is under Cost Centre 410, with a total forecast cost of $454,604.46.
Capital Item Justification Justification Criteria: Health & Safety Sub-Criteria: Maintenance Name of Report : Document Location:
AI summary The document outlines a capital item justification framework under 'Health & Safety' criteria, focusing on 'Maintenance' as a sub-criteria. It references a report titled 'Document Location:' but provides no further details or analysis.
Project: Removal of Frost Casing on Gulch Surge Tank U&U Item Description II Qty II Cost Est II Totals II 1 Contracts Frost Casing removal and disposal Security Fence Foundation for compressor building $5,000 &J Compressor building supply...
AI summary The document presents a project proposal for the removal of frost casing on the Gulch Surge Tank, including cost estimates for various components such as contracts, foundation work, and consulting fees, with a total project estimate of $454,605.