N-1CI C0082195 – LIN2 2025/26 Capacity Requirement - $4,392,251
5 passages
CI C0082195 LIN2 2025/26 Capacity Requirement NON-CONFIDENTIAL July 13, 2026
AI summary This document is a non-confidential submission related to the 2025/26 Capacity Requirement under the LIN2 proceeding, dated July 13, 2026. It appears to be part of a regulatory process involving capacity planning and electricity generation requirements.
July 10, 2026 CI Number: C0082195 Title: LIN2 2025/26 Capacity Requirement Start Date: 2025/01 In-Service Date: 2026/03 Final Cost Date: 2026/09 Function: Steam Forecast Amount: $4,392,251
AI summary The document outlines the LIN2 2025/26 Capacity Requirement, including its start date, in-service date, final cost date, function, and forecasted cost of $4,392,251.
Summary of Related CIs +/- 2 years: Pursuant to Section 11.2 of the Detailed CEJC, related CIs for Steam projects includes "work completed on the same asset (turbine, boiler, etc.) and on the same unit (Lingan Unit #3, for example)." - 202...
AI summary The document outlines related Capacity Improvement (CI) projects for Steam production at Lingan Unit 2, including specific financial figures and timelines for capacity requirements from 2023 to 2027. The depreciation group and estimated asset life are also mentioned, along with a reference to a Board Decision.
Title: LIN2 2025/26 Capacity Requirement Description Unit Quantity Unit Estimate Total Estimate Cost Support Reference Completed Similar Projects (FP#'s) Regular Labour Electrician PD 350 $ 403 $ 141,148 Engineering PD 50 $ 457 $ 22,844 Ma...
AI summary The document outlines the labor and material costs associated with the LIN2 2025/26 Capacity Requirement project, detailing estimates for various labor categories and materials needed for the project.
Document No: XXX-XX-XXXX-XXXX Project Cost Estimate Input Checklist and Maturity Matrix Equipment Replacement Required fields: Estimate Classification Project Name: LIN2 2025/26 Capacity Requirement Started or Preliminary Class 5 Class 4 C...
AI summary The document outlines a project cost estimate input checklist and maturity matrix for the LIN2 2025/26 Capacity Requirement. It includes sections on project scope, location, requirements, technology selection, and planning, with maturity levels defined for various deliverables.