M12959 Closed Electricity

Nova Scotia Power Inc. - CI C0082195 – LIN2 2025/26 Capacity Requirement - $4,392,251

Filed 07/13/2026 8 documents

What's happened

Filing Timeline

  • Document
    —
  • 24 Sep
    Decision
    NSEB Decision Letter now available approving $4,392,251 LIN2 2025/26 Capacity Requirement and directing ongoing Board oversight of Lingan Unit 2
  • 26 Aug
    RIR
    Nova Scotia Power filed responses to seven NSEB information requests in the Lingan Unit 2 2025/26 Capacity Requirement proceeding, confirming the 148 MW coal unit is needed through at least winter 2029/30 to maintain planning reserve margin.
  • 05 Aug
    Document
    NSEB Board Staff issue seven Information Requests to Nova Scotia Power on LIN2 2025/26 Capacity Requirement application (CI C0082195, $4,392,251)
  • 14 Jul
    Document
    Nova Scotia Power filed a $4,392,251 capital project application for Lingan Unit 2 refurbishment to maintain firm capacity through the 2025/26 winter season.

The filings themselves

Documents

Key documents 1 file
  • 103692 Decision Letter PDF · 09/24/2026
Exhibits 3 files
  • N-1 CI C0082195 – LIN2 2025/26 Capacity Requirement - $4,392,251 PDF · 07/14/2026
  • N-2 NSPI (NSEB) RIRs 1-7 - Redacted PDF · 08/26/2026
  • N-2(C) NSPI (NSEB) RIRs 1-7 - Confidential PDF · 08/26/2026
Other documents 4 files
  • 102744 Letter NSPI re: Capital Items Filed Outside the Quarter Package PDF · 07/13/2026
  • 103086 NSEB (NSPI) IR 1 to 7 PDF · 08/05/2026
  • 103342 Letter enclosing RIRs / confidentiality request PDF · 08/26/2026
  • 103692 Decision Letter PDF · 09/24/2026

What's discussed — click to drill in

Topics

Capacity Costs
13 passages across 7 documents
Capital Expenditures
11 passages across 6 documents
Capacity Market Participation
8 passages across 4 documents
Regulatory Approval Processes
8 passages across 4 documents
Planning Reserve Margin
6 passages across 2 documents
Cost Considerations
5 passages across 3 documents
Renewable Energy
5 passages across 4 documents
2025 Ace Plan
4 passages across 3 documents
Cost Recovery
4 passages across 3 documents
Generator Interconnection
4 passages across 3 documents
Infrastructure Planning
4 passages across 3 documents
Operating Expenses
4 passages across 4 documents
Energy Storage
3 passages across 3 documents
Generation Grid Resources
3 passages across 2 documents
System Reliability
3 passages across 2 documents
Planned Outage
2 passages across 2 documents
Rate Base
2 passages across 2 documents
2023-2026 DSM Plan
1 passages across 1 documents
Accounting Standards
1 passages across 1 documents
Asset Management
1 passages across 1 documents
Budgets And Targets
1 passages across 1 documents
Confidentiality
1 passages across 1 documents
Cost Deferral
1 passages across 1 documents
Depreciation Amortization
1 passages across 1 documents
Power Infrastructure
1 passages across 1 documents
Prudency Review
1 passages across 1 documents
Rates And Money
1 passages across 1 documents
Regulatory Compliance
1 passages across 1 documents
Regulatory Oversight
1 passages across 1 documents
Return On Equity
1 passages across 1 documents
Revenue Requirement
1 passages across 1 documents