Matter: Nova Scotia Power Inc. - CI C0082195 – LIN2 2025/26 Capacity Requirement - $4,392,251
3 passages 3 documents

Renewable Energy across all matters →

N-1CI C0082195 – LIN2 2025/26 Capacity Requirement - $4,392,251 1 passage
Why do this project this way? p. p. 3
Why do this project this way? NS Power is obligated to maintain sufficient firm capacity to meet its reliability obligations. Lingan Unit 2 was required for firm capacity for customers during the 2025/2026 season and is expected to be requ...

AI summary NS Power is maintaining Lingan Unit 2 to ensure firm capacity and system reliability until new resources are available. The Board has approved operating expenditures for LIN2 up to the end of 2024 but requires further approval for expenses beyond that date. The decision highlights the need for cost recovery and prudence in operations.

N-2NSPI (NSEB) RIRs 1-7 - Redacted 1 passage
REDACTED p. p. 1
REDACTED 2026 (Aug 1 - Dec 31) 2027 2028 Lingan 2 Generation (GWh) 2 (c) Please refer to the table below. Quarter Online Offline Net Gen (MWh) Q2 - 2025 April 29, 2025 May 6, 2025 9,460 Q3 - 2025 - - - November 5, 2025 November 25, 2025 50...

AI summary The text contains tables related to the Lingan 2 Generation, providing data on online and offline dates, as well as net generation in MWh for various quarters from 2025 to 2026. Some data is estimated and not yet finalized.

103086NSEB (NSPI) IR 1 to 7 1 passage
Request IR-1:
Request IR-1: - a) What is the current rated capacity (in MW) of the LIN2 generating unit? - b) Please provide an estimate of the power generation from this unit for 2026 to 2030. - c) Please extend the table requested by Board staff in IR...

AI summary The document contains three requests (IR-1, IR-2, IR-3) to Nova Scotia Power Incorporated (NSPOWER) regarding the capacity of the LIN2 generating unit, reserve margins for 2026-2027, and firm import options from New Brunswick and Newfoundland. It seeks information on generation estimates, energy substitution, and capacity planning.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →