LIN2 2025/26 Capacity Requirement project was necessary to provide firm capacity for the 2025/26 fall and winter season. Accordingly, the Board approves the project in the final amount of $4,392,251. The Board considers LIN2 to present a u...
AI summary The Board approved the LIN2 2025/26 Capacity Requirement project for $4,392,251, acknowledging the unique circumstances surrounding LIN2's role in ensuring adequate planning reserve margin during the winter. However, the Board emphasized the need for ongoing oversight of LIN2's expenses due to its impending retirement and the dynamic nature of future capacity requirements.