Matter: Nova Scotia Power Inc. - CI C0068659 – TRE5 – IP-LP Turbine Refurbishment - $2,963,160 (ATO)
2 passages 1 document

Renewable Energy across all matters →

103350NSEB (NSPI) IR-1 to IR-9 2 passages
Request IR-3:
Request IR-3: - In its response to NSUARB's IR-88 of 2025 ACE Plan, NS Power stated that some critical components could be utilized as future spares on Tufts Cove Unit 3 and Point Tupper Unit 2. - a) Please provide a table identifying all...

AI summary NS Power responded to NSUARB's IR-88 regarding the 2025 ACE Plan, suggesting that some components from the IP-LP refurbishment project may be used as spares for other units. The request asks for a detailed table of components, their potential reuse, and the retirement timelines of the receiving units.

Request IR-5:
Request IR-5: Beginning in 2020, please provide the annual operating cost of Trenton Unit 5 in $/MWh and total dollars for each year. Please compare these costs with similar NS Power thermal generating units.

AI summary Request IR-5 asks for the annual operating cost of Trenton Unit 5 in $/MWh and total dollars for each year, with a comparison to similar NS Power thermal generating units starting in 2020.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →